Adani Power Management Guidance Tracker
29 forward-looking guidance items tracked across 8 quarters.
Expansion
Targeting 30 GW capacity by 2029-30 from current 15 GW, including 1,600 MW Mahan Phase 2 (by June 2027) and 4,800 MW brownfield expansions.
Q1 FY25Inorganic acquisitions of Lanco Amarkantak and Coastal EnergenActiveAwaiting NCLT approval for resolution plans; Lanco adds 600 MW (tied up) and 1,320 MW under construction; Coastal adds 1,200 MW (600 MW tied up).
Q2 FY25Mahan Phase II completion by June 2027TrackedThe 1,600 MW ultra-supercritical expansion at Mahan is on track for commissioning by June 2027.
Q3 FY25Raipur expansion to commission within 4 yearsTrackedThe 1,600 MW Raipur expansion project (PPA with MSEDCL for 1,496 MW) is planned to commission within 4 years, though PPA allows 5 years.
Q3 FY25Korba (Lanco) expansion to commission in ~30 monthsTrackedThe 1,320 MW Korba expansion project is expected to commission in about 30 months from the call date, with estimated CapEx of INR 10,000 crore.
Q1 FY26Capacity expansion target of 12,520 MW by 2030TrackedManagement reiterated target to add 12,520 MW by 2030, with 4,800 MW under execution. Boiler, turbine, and generator supplies locked for entire 11.2 GW new capacity.
Q2 FY26Godda plant to connect to Indian grid by December 2025ActiveThe Godda power plant is expected to be connected to the Indian grid by December 2025, allowing sales under certain conditions.
Q3 FY26Capacity expansion of 23.7 GW by FY32TrackedPlanned addition of 23.7 GW thermal capacity, with 2.9 GW commissioning next fiscal, 2.4 GW in FY28, 2.4 GW in FY29, 8 GW in FY30, 5.6 GW in FY31, and 2.4 GW in FY32.
Q3 FY26Korba Phase 2 commissioning by end of next fiscalTrackedFirst unit of Korba Phase 2 expected around mid-next year, second unit by end of next fiscal.
Q4 FY26Korba Phase 2 commissioning in Q2 FY27ActiveThe 1.32 GW Korba Phase 2 project is expected to commission between June and September 2026.
Q4 FY26Mahan commissioning by Q4 FY27/Q1 FY28TrackedFirst unit of Mahan (1.6 GW) likely by end of FY27, second unit six months later.
Revenue
New projects will have 80% capacity tied to long-term PPAs (25-year duration) and 20% kept for merchant sales.
Q2 FY2580% PPA tie-up for new capacityTrackedManagement aims to secure long-term PPAs for 80% of new capacity, keeping 20% for merchant sales to balance risk and reward.
Q2 FY26Merchant tariff expected to average ~INR 6/unit in H2 FY26ActiveManagement expects merchant realization to recover to around INR 6 per unit in the second half, from INR 5.37 in Q2.
Growth
Plans to double capacity from ~15 GW to 30.67 GW through organic expansion (Mahan Phase II, Raipur, Raigarh, Mirzapur) and acquisitions (Lanco, Coastal).
Q3 FY25Rohne coal mine to supply 5 MTPA after 2 yearsTrackedThe Rohne mine, acquired from Adani Enterprises, will supply 5 million tons of coal per annum after two years for the Mahan plant's untied capacity.
Q3 FY25Target 30 GW operating capacity by 2030TrackedManagement reiterated the target to achieve more than 30 GW of operating capacity by 2030, with BTG orders placed for 11.2 GW.
Q4 FY25Mahan Phase II commissioning by March 2027TrackedThe 1,600 MW Mahan expansion project is expected to be commissioned around March or April 2027.
Q4 FY25Capacity expansion to 30,670 MW by 2030TrackedAdani Power targets to increase its total capacity to 30,670 MW by 2030 through brownfield expansions.
Q2 FY26First 12 GW of expansion on track; 3 GW commissioning next yearTrackedThe first 12 GW of the 23.5 GW expansion is on schedule, with ~3 GW expected to commission in FY27, followed by 2.4 GW, 3.2 GW, and 7.2 GW in subsequent years.
Q3 FY26Reduce open capacity to 3-4% over 6-7 yearsTrackedManagement targets reducing merchant exposure from current 10% to 3-4% over the medium term by signing more long-term PPAs.
Q4 FY26EBITDA target of ₹50,000 crore by FY30-31TrackedManagement expects EBITDA to reach ₹50,000 crore by 2030-31, driven by capacity expansion and new PPAs.
Capex
The company plans to spend INR 13,000 crore on capital expenditure in FY2026 for its expansion projects.
Q1 FY26No SGD requirement for new plants, reducing project costTrackedFollowing government notification, SGD will be dropped from new plants except Mahan and Raipur, lowering capital cost.
Q2 FY26Total CapEx for 23.5 GW expansion ~INR 2 lakh croreTrackedThe estimated capital expenditure for the entire 23.5 GW capacity expansion is approximately INR 2 lakh crore.
Q4 FY26Capex of ₹25,000 cr in FY27 and ₹33,000 cr in FY28TrackedCapital expenditure for capacity expansion estimated at ₹25,000 crore in FY27 and ₹33,000 crore in FY28.
Other
Management stated that the entire capex plan will be funded from internal accruals without additional debt.
Q1 FY26Deroli mine production to start by Sep-Oct 2025ActiveCEO confirmed production from Deroli mine is on track to start by September or October 2025.