ConCallIQ
Go Pro

Powergrid FY25 Annual Earnings Summary

4 quarters covered · ₹47,460 Cr revenue · ₹15,522 Cr PAT · 0.0% average EBITDA margin.

Total annual revenue: ₹47,460 Cr
Annual PAT: ₹15,522 Cr
Average margin: 0.0%
Promise delivery: 0%

Quarter-by-quarter progression

QuarterRevenuePATMarginSentiment
Q1 FY25₹11,280 Cr₹3,724 Crbullish
Q2 FY25₹11,846 Cr₹3,793 Crneutral
Q3 FY25₹11,743 Cr₹3,862 Crbullish
Q4 FY25₹12,591 Cr₹4,143 Crbullish

Management promises made during the year

Intrastate JV pipeline of INR 10,000 crore from Rajasthan

Current-quarter commentary contains related risk or weakness, so the promise appears not to have been delivered yet.

Q1 FY25
missed
FY25 CapEx raised to INR 18,000 crore

Current-quarter commentary contains related risk or weakness, so the promise appears not to have been delivered yet.

Q2 FY25
missed
Data center Phase I commissioning in Q4 FY25

Current-quarter commentary contains related risk or weakness, so the promise appears not to have been delivered yet.

Q2 FY25
missed
CapEx target of INR 18,000 crore for FY25, likely to exceed INR 20,000 crore

Current-quarter commentary contains related risk or weakness, so the promise appears not to have been delivered yet.

Q3 FY25
missed
FY25 CapEx target of INR 23,000 crore

Current-quarter commentary contains related risk or weakness, so the promise appears not to have been delivered yet.

Q4 FY25
missed
FY25 capitalization target of INR 18,000 crore

Current-quarter commentary contains related risk or weakness, so the promise appears not to have been delivered yet.

Q4 FY25
missed

Risks flagged during the year

Q1 FY25 · high

Management acknowledged that transformers, reactors, and GIS are in tight supply, with costs rising 70-80% since 2017-18, potentially delaying projects.

Q1 FY25 · medium

The offshore wind evacuation projects (INR 13,100 crore total) are India's first, and management noted costs may be higher than routine projects, posing execution risk.

Q1 FY25 · medium

Management could not confirm if the 125 GW RE requirement for green hydrogen is included in the National Electricity Plan, indicating potential policy uncertainty.

Q2 FY25 · medium

EESL contributed a loss of INR 100 crore in H1 FY25 due to mounting receivables and interest costs, with no clear timeline for reversal.

Q2 FY25 · medium

New CERC tariff regulation (2024-29) reduced O&M charges by INR 600 crore annually, impacting profitability by ~INR 300 crore in H1.

Q2 FY25 · medium

Revenue from legacy RTM projects is declining due to lower depreciation and interest, partially offsetting growth from new TBCB projects.

Q3 FY25 · medium

Management acknowledged challenges in land acquisition (ROW issues) and supply of high-voltage transformers and GIS equipment, which could delay project commissioning beyond the typical two-year timeline.

Q3 FY25 · medium

The CERC tariff true-up impacted Q3 PAT by INR 140 crore, and the nine-month impact is ~INR 440 crore. This regulatory adjustment could continue to weigh on earnings.

Q3 FY25 · medium

Management reduced the interim dividend per share (from INR 4.5 to INR 3.25) to conserve equity for the growing CapEx pipeline. Further reductions are possible if CapEx continues to rise.

Q4 FY25 · medium

ROW compensation policy changes and state-level adoption delays caused commissioning slippages in FY25; may persist.

Q4 FY25 · medium

Current TBCB pipeline is only INR 45,000-46,000 crore, significantly lower than INR 92,000 crore won in FY25, which could slow order book growth.

Q4 FY25 · medium

ROE dipped ~100bps YoY as net worth grew faster than profits; further dilution possible if CapEx ramp-up requires equity.

What changed through the year

G

Q1 FY25 · FY25 CapEx raised to INR 18,000 crore

Management increased CapEx guidance from INR 15,000 crore to INR 18,000 crore due to new project wins requiring spending this fiscal.

G

Q1 FY25 · Capitalization target of INR 18,000 crore in FY25

Target to commission projects worth INR 18,000 crore in FY25, with INR 25,000-30,000 crore expected in each of FY26 and FY27.

G

Q1 FY25 · Bidding pipeline of INR 100,000+ crore

Over INR 100,000 crore of transmission projects are in the pipeline, with 70-80% expected to be awarded in FY25.

G

Q1 FY25 · Data center Phase I commissioning in Q4 FY25

The 1,000-rack data center at Manesar is expected to be commercially available by Q4 FY25, with Phase II of INR 2,000 crore planned.

G

Q2 FY25 · CapEx target of INR 18,000 crore for FY25, likely to exceed INR 20,000 crore

Management expects CapEx to be at least INR 18,000 crore this fiscal, with potential to exceed INR 20,000 crore.

G

Q2 FY25 · CapEx of INR 25,000-30,000 crore in FY26

Next fiscal CapEx is guided to be between INR 25,000 and INR 30,000 crore.

G

Q2 FY25 · Capitalization to reach INR 35,000-40,000 crore in 2-3 years

Capitalization is expected to ramp up to INR 35,000-40,000 crore per annum as projects are commissioned.

G

Q2 FY25 · Target win rate of ~50% in TBCB projects

Management expects to win about 50% of upcoming TBCB projects, translating to INR 192,000 crore additional orders by 2032.

G

Q3 FY25 · FY25 CapEx target of INR 23,000 crore

Management reiterated the FY25 CapEx plan of INR 23,000 crore, with INR 19,480 crore already spent by January 31, 2025.

G

Q3 FY25 · FY25 capitalization target of INR 18,000 crore

Capitalization target for FY25 is INR 18,000 crore, with INR 7,906 crore achieved by January 31, 2025. Management expects to commission ~INR 10,000 crore in the remaining 45-50 days.

G

Q3 FY25 · FY26 CapEx guidance of INR 28,000-30,000 crore

For FY26, CapEx is expected to be in the range of INR 28,000-30,000 crore, driven by the strong project pipeline.

G

Q3 FY25 · FY27 CapEx guidance of INR 35,000 crore

For FY27, CapEx is expected to be around INR 35,000 crore, with potential upside from additional HVDC projects.

G

Q4 FY25 · CapEx of INR 28,000 crore for FY26

Management guided CapEx of INR 28,000 crore for FY26, with potential to increase to INR 30,000 crore based on project wins.

G

Q4 FY25 · CapEx of INR 35,000 crore for FY27 and INR 45,000 crore for FY28

Management provided CapEx targets of INR 35,000 crore for FY27 and INR 45,000 crore for FY28.

G

Q4 FY25 · Capitalization of INR 23,000-25,000 crore in FY26

Management expects capitalization of INR 23,000-25,000 crore in FY26, up from INR 9,014 crore in FY25.

G

Q4 FY25 · Dividend payout may reduce further

Management indicated dividend per share could reduce from INR 9 in FY25 due to higher CapEx requirements.