ConCallIQ
Go Pro
POWERGRID Energy 12 Nov 2024

Power Grid Corporation — Q2 FY25

Power Grid reported consolidated Q2 FY25 revenue of INR 11,846 crore (+2.7% YoY) and PAT of INR 3,793 crore (+0.3% YoY), with muted growth due to a INR 300 crore O&M cost reduction under the new CERC tariff regulation and a INR 100 crore loss from associate...

neutral medium
Compare with...
Revenue ₹11,278 Cr +2.74%
EBITDA
PAT ₹3,793 Cr +0.32%
EBITDA Margin 85%
Duration
Read Time 1 min read

✓ Verified against BSE filing

2-Minute Summary

✦ AI-Generated from Full Transcript

Power Grid reported consolidated Q2 FY25 revenue of INR 11,846 crore (+2.7% YoY) and PAT of INR 3,793 crore (+0.3% YoY), with muted growth due to a INR 300 crore O&M cost reduction under the new CERC tariff regulation and a INR 100 crore loss from associate EESL. Management highlighted a strong pipeline of INR 143,295 crore projects in hand and expects CapEx to rise to INR 25,000-30,000 crore in FY26, with capitalization reaching INR 35,000-40,000 crore in 2-3 years. Key growth drivers include the National Electricity Plan requiring INR 9.16 lakh crore transmission investment by 2032, with Power Grid targeting a 50% win rate. Risks include competitive pressure in TBCB projects and continued EESL losses.

Promises0 met · 2 missedRisks4 trackedTranscriptfull text
Research workspace

Focused Modules

Promises 2 promises

Promise Tracker

0 delivered, 0 close, 2 missed.

View Promises →
!Risks 4 risks

Risk Intelligence

EESL associate losses continue

View Risks →
Transcript Full text

Call Transcript

Full transcript text is available on this route.

Read Transcript →

Quarter Snapshot

Transmission System Availability 99.80%
+5bps YoY

Achieved 99.80% availability in H1 FY25, above the incentive threshold of 99.75%.

Projects in Hand INR 143,295 crore
+INR 38,008 crore YoY

Includes RTM, TBCB, and new projects like Leh-Pang HVDC and offshore wind.

TBCB Projects Won in Q2 8 projects
+8 projects YoY

Won 8 out of 13 TBCB projects bid in Q2, representing 78% of annual tariff.

Smart Meters Installed 1 lakh
N/A

Installed 1 lakh smart meters out of 63 lakh planned in Gujarat projects.

What Changed vs Last Quarter

Comparing Q2 FY25 vs Q1 FY25
2 new guidance2 dropped4 new risk4 risk resolved
NEW
Capitalization to reach INR 35,000-40,000 crore in 2-3 years

Capitalization is expected to ramp up to INR 35,000-40,000 crore per annum as projects are commissioned.

NEW
Target win rate of ~50% in TBCB projects

Management expects to win about 50% of upcoming TBCB projects, translating to INR 192,000 crore additional orders by 2032.

UPDATED
CapEx target of INR 18,000 crore for FY25, likely to exceed INR 20,000 crore

Management expects CapEx to be at least INR 18,000 crore this fiscal, with potential to exceed INR 20,000 crore.

UPDATED
CapEx of INR 25,000-30,000 crore in FY26

Next fiscal CapEx is guided to be between INR 25,000 and INR 30,000 crore.

DROPPED
Bidding pipeline of INR 100,000+ crore

Over INR 100,000 crore of transmission projects are in the pipeline, with 70-80% expected to be awarded in FY25.

DROPPED
Data center Phase I commissioning in Q4 FY25

The 1,000-rack data center at Manesar is expected to be commercially available by Q4 FY25, with Phase II of INR 2,000 crore planned.

NEW RISK
EESL associate losses continue

EESL contributed a loss of INR 100 crore in H1 FY25 due to mounting receivables and interest costs, with no clear timeline for reversal.

NEW RISK
O&M cost reduction under new CERC regulation

New CERC tariff regulation (2024-29) reduced O&M charges by INR 600 crore annually, impacting profitability by ~INR 300 crore in H1.

NEW RISK
Declining RTM revenue offsets TBCB gains

Revenue from legacy RTM projects is declining due to lower depreciation and interest, partially offsetting growth from new TBCB projects.

NEW RISK
Competitive pressure in TBCB bidding

Analyst raised concern about potential ROE compression in TBCB projects due to competitive bidding, though management downplayed the risk.

RISK GONE
Equipment supply constraints for transformers and GIS

Management acknowledged that transformers, reactors, and GIS are in tight supply, with costs rising 70-80% since 2017-18, potentially delaying projects.

RISK GONE
Cost overruns on first-of-its-kind offshore wind projects

The offshore wind evacuation projects (INR 13,100 crore total) are India's first, and management noted costs may be higher than routine projects, posing execution risk.

RISK GONE
Dividend dependency on SPVs impacting standalone profits

Analyst noted flattish standalone PAT due to lower dividends from SPVs; management confirmed this but said consolidated view is more relevant going forward.

RISK GONE
Green hydrogen transmission capacity not yet in NEP

Management could not confirm if the 125 GW RE requirement for green hydrogen is included in the National Electricity Plan, indicating potential policy uncertainty.

🤫 Topics management stopped discussing

Supply chain constraints for STATCOM and HVDC equipment

Mentioned in Q1 FY25, Q2 FY24, Q3 FY24

Management acknowledged that transformers, reactors, and GIS are in tight supply, with costs rising 70-80% since 2017-18, potentially delaying projects.

Fast read

Guidance and risk preview

Top guidance CapEx target of INR 18,000 crore for FY25, likely to exceed INR 20,000 crore

Management expects CapEx to be at least INR 18,000 crore this fiscal, with potential to exceed INR 20,000 crore.

Top risk EESL associate losses continue

EESL contributed a loss of INR 100 crore in H1 FY25 due to mounting receivables and interest costs, with no clear timeline for reversal.

View Risks →