Adani Power reported Q3 FY26 revenue of INR 12,717 crore, down 5.3% YoY, due to lower power selling rates and weaker merchant prices.
Financial stats pending filing verification
Indian management teams deliver on roughly 12% of specific earnings-call promises. A low score does not indicate dishonesty — it reflects how aspirational forward guidance typically is.
Merchant tariff expected to average ~INR 6/unit in H2 FY26
Management expects merchant realization to recover to around INR 6 per unit in the second half, from INR 5.37 in Q2.
Current-quarter commentary contains related risk or weakness, so the promise appears not to have been delivered yet.
heuristic_v1Godda plant to connect to Indian grid by December 2025
The Godda power plant is expected to be connected to the Indian grid by December 2025, allowing sales under certain conditions.
Current-quarter commentary contains related risk or weakness, so the promise appears not to have been delivered yet.