ConCallIQ
Go Pro

Powergrid FY24 Annual Earnings Summary

4 quarters covered · ₹36,739 Cr revenue · ₹12,085 Cr PAT · 21.1% average EBITDA margin.

Total annual revenue: ₹36,739 Cr
Annual PAT: ₹12,085 Cr
Average margin: 21.1%
Promise delivery: 0%

Quarter-by-quarter progression

QuarterRevenuePATMarginSentiment
Q1 FY24₹1,135 Cr₹148 Crbullish
Q2 FY24₹11,530 Cr₹3,781 Crbullish
Q3 FY24₹11,820 Cr₹4,028 Crbullish
Q4 FY24₹12,254 Cr₹4,128 Cr84.5%bullish

Management promises made during the year

Commission phase 1 of biogas plant in FY24

The current-quarter record did not contain enough evidence of delivery; the item remains delayed for follow-up.

Q2 FY24
delayed
FY24 CapEx target raised to ~INR 10,000 crore

Current-quarter commentary contains related risk or weakness, so the promise appears not to have been delivered yet.

Q3 FY24
missed

Risks flagged during the year

Q2 FY24 · high

High-altitude terrain and extreme weather limit working months to 5-6 per year, posing timeline risks.

Q1 FY24 · medium

Industrial consumers are switching to cheaper propane/LPG, pressuring PNG volumes. Management responded by offering competitive pricing.

Q1 FY24 · medium

APM allocation deficit was 14% in Q1, trending down but could remain a margin headwind if domestic gas supply doesn't keep pace with demand.

Q2 FY24 · medium

Management acknowledged challenges in transformer and HVDC equipment availability due to global demand, though insulated by firm-price contracts.

Q2 FY24 · medium

CERC draft regulations expected by Nov-Dec 2023; any adverse changes could impact regulated equity returns.

Q3 FY24 · medium

Draft regulations propose changes to O&M norms and reduce ROE to 15% for new assets. Management expects minimal impact but discussions ongoing.

Q3 FY24 · medium

Management acknowledged potential challenges in transformer and GIS supply, but noted government actions to develop more vendors.

Q3 FY24 · medium

Analyst flagged that the INR 310,000 crore ISTS target over FY22-27 appears aggressive given the need for rapid awarding and execution.

Q4 FY24 · medium

Analyst noted a deteriorating trend in CapEx-to-annuity ratios for TBCB projects, which could pressure IRRs. Management acknowledged but maintained 10-12% IRR target.

Q1 FY24 · low

Analyst raised concern about potential price regulation; management dismissed it, citing natural competition, but risk remains if government intervenes.

Q2 FY24 · low

H1 FY24 saw fewer bids; management expects pick-up in H2, but any delay could impact order book.

Q3 FY24 · low

The project has a long gestation of ~5 years from order placement, with commissioning expected only by FY2030, posing execution risk.

What changed through the year

G

Q1 FY24 · Set up 3,000 EV charging points

Target to install 3,000 charging points across strategic locations in the near future, up from 141 currently.

G

Q1 FY24 · Commission phase 1 of biogas plant in FY24

One of India's largest biogas plants in Uttar Pradesh will commission phase 1 in FY24.

G

Q1 FY24 · Accelerate CNG station rollout in ODO/DODO format

Focus on adding more CNG stations in ODO and DODO formats to expand network rapidly.

G

Q2 FY24 · FY24 CapEx target raised to ~INR 10,000 crore

Management increased CapEx guidance from INR 8,800 crore to ~INR 10,000 crore, split equally between RTM and TBCB projects.

G

Q2 FY24 · FY25 CapEx target of INR 12,500-15,000 crore

Initial CapEx target for FY25 is INR 12,500 crore, with potential upside from HVDC projects.

G

Q2 FY24 · FY25 capitalization target of INR 17,000 crore

Capitalization expected to rise to ~INR 17,000 crore in FY25 from INR 10,000 crore in FY24.

G

Q2 FY24 · Leh-Ladakh project award by Q4 FY25 or Q1 FY26

FEED studies ongoing; award expected in late FY25 or early FY26.

G

Q3 FY24 · CAPEX of INR 15,000 crore+ in FY25

Management guided for CAPEX exceeding INR 15,000 crore in FY25, driven by execution of existing order book.

G

Q3 FY24 · CAPEX of INR 20,000 crore+ in FY26

CAPEX expected to rise further to over INR 20,000 crore in FY26, supported by large project pipeline.

G

Q3 FY24 · Capitalization of INR 16,000-17,000 crore in FY25

Capitalization is expected to be around INR 16,000-17,000 crore in FY25, up from ~INR 8,500 crore in FY24.

G

Q3 FY24 · Dividend payout maintained at current level

Management confirmed no reduction in dividend payout, with asset monetization through securitization to fund equity requirements.

G

Q4 FY24 · FY25 CapEx target of INR 17,000 crore

Management guided CapEx of ~INR 17,000 crore for FY25, up from INR 12,500 crore in FY24, with potential to exceed.

G

Q4 FY24 · Capitalization target of INR 15,000-16,000 crore in FY25

Capitalization is expected to double from INR 7,638 crore in FY24 to around INR 15,000-16,000 crore in FY25.

G

Q4 FY24 · Intrastate JV pipeline of INR 10,000 crore from Rajasthan

JV with RVPN targets INR 10,000 crore of intrastate transmission projects over 3-4 years, with INR 1,500-2,000 crore in next 2-3 months.

G

Q4 FY24 · Dividend payout to remain healthy

Management expects no reduction in dividend despite higher CapEx, citing sufficient cash flows from profits.