ConCallIQ
Go Pro
POWERGRID Energy 01 Nov 2023

Powergrid Ltd — Q2 FY24

PowerGrid reported a steady Q2 FY24 with consolidated revenue of INR 11,530 crore (up ~1.6% YoY) and PAT of INR 3,781 crore (up ~3.6% YoY), driven by regulated transmission assets and higher tariff realization.

bullish high
Revenue ₹11,530 Cr +1.6%
EBITDA
PAT ₹3,781 Cr +3.6%
EBITDA Margin
Duration
Read Time 1 min read

Financial stats pending filing verification

2-Minute Summary

✦ AI-Generated from Full Transcript

PowerGrid reported a steady Q2 FY24 with consolidated revenue of INR 11,530 crore (up ~1.6% YoY) and PAT of INR 3,781 crore (up ~3.6% YoY), driven by regulated transmission assets and higher tariff realization. The company won five TBCB projects in H1 FY24 with an annual tariff of INR 703 crore, and the Leh-Ladakh project (INR 20,700 crore, 40% grant) is progressing with FEED studies. Management guided FY24 CapEx to ~INR 10,000 crore (up from INR 8,800 crore) and FY25 CapEx to INR 12,500-15,000 crore, supported by a strong pipeline of INR 60,000 crore under bidding. Risks include supply chain constraints for STATCOM/HVDC equipment and regulatory uncertainty around the new tariff control period.

Key Numbers

TBCB projects won in H1 FY24 5
+150% YoY

Won 5 TBCB projects vs 2 in H1 FY23, with annual tariff of INR 703 crore.

System availability 99.85%
+10bps YoY

Maintained high availability, improving from 99.75% in H1 FY23.

Work in hand INR 60,000-65,000 crore
+20% YoY

Includes recent TBCB wins and RTM projects; excludes Leh-Ladakh.

Debt-to-equity ratio 58:42
-100bps YoY

Improved from 59:41 in Q1 FY24 and 61:39 in Q2 FY23.

What Changed vs Last Quarter

Comparing Q2 FY24 vs Q1 FY24
4 new guidance3 dropped4 new risk3 risk resolved
NEW
FY24 CapEx target raised to ~INR 10,000 crore

Management increased CapEx guidance from INR 8,800 crore to ~INR 10,000 crore, split equally between RTM and TBCB projects.

NEW
FY25 CapEx target of INR 12,500-15,000 crore

Initial CapEx target for FY25 is INR 12,500 crore, with potential upside from HVDC projects.

NEW
FY25 capitalization target of INR 17,000 crore

Capitalization expected to rise to ~INR 17,000 crore in FY25 from INR 10,000 crore in FY24.

NEW
Leh-Ladakh project award by Q4 FY25 or Q1 FY26

FEED studies ongoing; award expected in late FY25 or early FY26.

DROPPED
Set up 3,000 EV charging points

Target to install 3,000 charging points across strategic locations in the near future, up from 141 currently.

DROPPED
Commission phase 1 of biogas plant in FY24

One of India's largest biogas plants in Uttar Pradesh will commission phase 1 in FY24.

DROPPED
Accelerate CNG station rollout in ODO/DODO format

Focus on adding more CNG stations in ODO and DODO formats to expand network rapidly.

NEW RISK
Supply chain constraints for STATCOM and HVDC equipment

Management acknowledged challenges in transformer and HVDC equipment availability due to global demand, though insulated by firm-price contracts.

NEW RISK
Regulatory uncertainty on new tariff control period

CERC draft regulations expected by Nov-Dec 2023; any adverse changes could impact regulated equity returns.

NEW RISK
Execution risk in Leh-Ladakh project

High-altitude terrain and extreme weather limit working months to 5-6 per year, posing timeline risks.

NEW RISK
Slowdown in TBCB bidding activity

H1 FY24 saw fewer bids; management expects pick-up in H2, but any delay could impact order book.

RISK GONE
Propane competition intensifying

Industrial consumers are switching to cheaper propane/LPG, pressuring PNG volumes. Management responded by offering competitive pricing.

RISK GONE
APM gas allocation deficit may persist

APM allocation deficit was 14% in Q1, trending down but could remain a margin headwind if domestic gas supply doesn't keep pace with demand.

RISK GONE
Regulatory risk on CNG/PNG pricing

Analyst raised concern about potential price regulation; management dismissed it, citing natural competition, but risk remains if government intervenes.

Management Guidance

G

FY24 CapEx target raised to ~INR 10,000 crore

Management increased CapEx guidance from INR 8,800 crore to ~INR 10,000 crore, split equally between RTM and TBCB projects.

Management guidance capex
G

FY25 CapEx target of INR 12,500-15,000 crore

Initial CapEx target for FY25 is INR 12,500 crore, with potential upside from HVDC projects.

Management guidance capex
G

FY25 capitalization target of INR 17,000 crore

Capitalization expected to rise to ~INR 17,000 crore in FY25 from INR 10,000 crore in FY24.

Management guidance growth
G

Leh-Ladakh project award by Q4 FY25 or Q1 FY26

FEED studies ongoing; award expected in late FY25 or early FY26.

Management guidance expansion

Key Risks

R

Supply chain constraints for STATCOM and HVDC equipment

Management acknowledged challenges in transformer and HVDC equipment availability due to global demand, though insulated by firm-price contracts.

medium · analyst_question
R

Regulatory uncertainty on new tariff control period

CERC draft regulations expected by Nov-Dec 2023; any adverse changes could impact regulated equity returns.

medium · analyst_question
R

Execution risk in Leh-Ladakh project

High-altitude terrain and extreme weather limit working months to 5-6 per year, posing timeline risks.

high · management_commentary
R

Slowdown in TBCB bidding activity

H1 FY24 saw fewer bids; management expects pick-up in H2, but any delay could impact order book.

low · analyst_question

Notable Quotes

We have a lot of CapEx is on the growing side, and we hope that it crosses at least INR 15,000 next year.
Shri Ravisankar · Director and CFO, Power Grid
The system availability continues to be above 99%.
Shri Ravisankar · Director and CFO, Power Grid
We are setting up one data center in Manesar as a pilot project. So the award is under progress, and then maybe in another 12-15 months, it is expected to complete.
Shri Ravisankar · Director and CFO, Power Grid

Frequently Asked Questions

What was Powergrid's revenue in Q2 FY24?

Powergrid reported revenue of ₹11,530 Cr in Q2 FY24, representing a +1.6% change compared to the same quarter last year.

What guidance did Powergrid management give for FY25?

FY24 CapEx target raised to ~INR 10,000 crore: Management increased CapEx guidance from INR 8,800 crore to ~INR 10,000 crore, split equally between RTM and TBCB projects. FY25 CapEx target of INR 12,500-15,000 crore: Initial CapEx target for FY25 is INR 12,500 crore, with potential upside from HVDC projects. FY25 capitalization target of INR 17,000 crore: Capitalization expected to rise to ~INR 17,000 crore in FY25 from INR 10,000 crore in FY24. Leh-Ladakh project award by Q4 FY25 or Q1 FY26: FEED studies ongoing; award expected in late FY25 or early FY26.

What are the key risks for Powergrid in FY25?

Key risks include Supply chain constraints for STATCOM and HVDC equipment — Management acknowledged challenges in transformer and HVDC equipment availability due to global demand, though insulated by firm-price contracts.; Regulatory uncertainty on new tariff control period — CERC draft regulations expected by Nov-Dec 2023; any adverse changes could impact regulated equity returns.; Execution risk in Leh-Ladakh project — High-altitude terrain and extreme weather limit working months to 5-6 per year, posing timeline risks.; Slowdown in TBCB bidding activity — H1 FY24 saw fewer bids; management expects pick-up in H2, but any delay could impact order book..

Did Powergrid meet its previous quarter's guidance?

Of 1 tracked promise, management 0 met, 0 close, 0 missed, 1 delayed.

Where can I read the full Powergrid Q2 FY24 concall transcript?

The full earnings conference call transcript or source release is available on the linked source material. This page provides an AI-generated summary with filing verification status shown on the financial stats.