ConCallIQ
Go Pro
NTPC Diversified 30 Oct 2024

NTPC — Q2 FY25

NTPC delivered a strong Q2 FY25 with standalone PAT of ₹4,649 crore, up 19.66% YoY, driven by higher generation and cost pass-through mechanisms.

bullish high
Compare with...
Revenue ₹44,706 Cr
EBITDA
PAT ₹5,380 Cr +19.66%
EBITDA Margin 26%
Duration
Read Time 1 min read

✓ Verified against BSE filing

2-Minute Summary

✦ AI-Generated from Full Transcript

NTPC delivered a strong Q2 FY25 with standalone PAT of ₹4,649 crore, up 19.66% YoY, driven by higher generation and cost pass-through mechanisms. Revenue was slightly lower due to a decline in average coal prices, but operational efficiency remained robust with coal PLF at 76.31% vs national average of 70.63%. The company is aggressively expanding its renewable portfolio through NTPC Green Energy (NGEL), targeting 3 GW RE addition in FY25, 5 GW in FY26, and 8 GW in FY27, aiming for 60 GW by FY32. On thermal, 13.6 GW of new capacity is planned for award by FY27, with 8.8 GW already bid out. The NGEL IPO is on track for Q3. Key risks include potential policy changes on FGD installations and rising thermal project costs due to air-cooled condenser requirements.

Promises0 met · 3 missedRisks4 trackedTranscriptfull text
Research workspace

Focused Modules

Promises 3 promises

Promise Tracker

0 delivered, 0 close, 3 missed.

View Promises →
!Risks 4 risks

Risk Intelligence

FGD policy uncertainty

View Risks →
Transcript Full text

Call Transcript

Full transcript text is available on this route.

Read Transcript →

Quarter Snapshot

Coal PLF 76.31%
+570bps vs national avg

NTPC's coal plant load factor outperformed the national average of 70.63% in H1 FY25.

Coal Production 19.23 MMT
+19.74% YoY

Highest ever coal production in H1 FY25, up from 16.06 MMT in H1 FY24.

RE Capacity Addition Target 3 GW
FY25 target

NTPC Green Energy plans to add 3 GW renewable capacity in FY25, 5 GW in FY26, and 8 GW in FY27.

Thermal Capacity Under Construction 11.16 GW
plus 13.6 GW planned

11.16 GW thermal capacity under construction; additional 13.6 GW to be awarded by FY27.

What Changed vs Last Quarter

Comparing Q2 FY25 vs Q4 FY24
2 new guidance2 dropped4 new risk4 risk resolved
NEW
Thermal capacity awards of 13.6 GW by FY27

8.8 GW already bid out (award by Dec 2024), balance 4.8 GW in next two months; total 13.6 GW thermal capacity to be awarded by FY27.

NEW
NGEL IPO expected in Q3 FY25

Draft red herring prospectus filed; IPO process on track for completion in Q3 FY25.

UPDATED
RE capacity addition of 3 GW in FY25, 5 GW in FY26, 8 GW in FY27

NTPC Green Energy will add 3 GW renewable capacity in FY25, 5 GW in FY26, and 8 GW in FY27, targeting 60 GW by FY32.

UPDATED
Coal production target of 67 MMT by FY29

NTPC group coal production to increase from 40 MMT in FY25 to about 67 MMT by FY29.

DROPPED
Thermal capacity ordering plan: 15.2 GW over FY25-FY27

10.4 GW to be tendered in FY25, 3.2 GW in FY26, 1.6 GW in FY27. Includes Sipat, Darlipali, Meja, etc.

DROPPED
NGEL IPO planned for October-November 2024

DRHP filing post-June 2024; NTPC to remain holding company post-IPO.

NEW RISK
FGD policy uncertainty

Government may stop issuing new FGD tenders; though NTPC is hedged via cost-plus mechanism, any change could impact project timelines.

NEW RISK
Rising thermal project costs

CapEx per MW for new thermal projects has risen beyond ₹12 crore due to mandatory air-cooled condensers and limited bidders.

NEW RISK
Under-recovery from disincentives

Under-recovery increased to ₹495 crore in Q2 from ₹381 crore last year due to higher planned outages (6.12% vs 5.19%).

NEW RISK
PPA signing delays for thermal projects

Some thermal projects (e.g., Gadarwara Stage-II) have only 68% PPA consent; balance expected in four months but could slip.

RISK GONE
Renewable execution delays

Commissioning of renewable projects slower than guided due to module import clearance delays and land acquisition issues.

RISK GONE
Under-recovery from disallowances

INR 776 crores under-recovery in FY24 due to lower availability at Barh and Barauni plants; though management expects reduction.

RISK GONE
Dividend from subsidiaries declined

Dividend from JVs and subsidiaries fell from INR 2,336 crores in FY23 to INR 1,630 crores in FY24 due to retained earnings for reinvestment.

RISK GONE
PPA availability for new thermal capacity

Out of 15.2 GW planned, only 8 GW has PPAs signed; remaining 7 GW needs tie-up with states/ministry.

🤫 Topics management stopped discussing

Execution delays in renewable projects

Mentioned in Q2 FY24, Q3 FY24, Q4 FY24

Commissioning of renewable projects slower than guided due to module import clearance delays and land acquisition issues.

Thermal capacity ordering plan: 15.2 GW over FY25-FY27

Mentioned in Q2 FY24, Q3 FY24, Q4 FY24

10.4 GW to be tendered in FY25, 3.2 GW in FY26, 1.6 GW in FY27. Includes Sipat, Darlipali, Meja, etc.

Renewable capacity target of ~15 GW by FY26

Mentioned in Q2 FY24, Q3 FY24

Despite delays, management reiterated the target of 15 GW operational renewable capacity by FY26.

Fast read

Guidance and risk preview

Top guidance RE capacity addition of 3 GW in FY25, 5 GW in FY26, 8 GW in FY27

NTPC Green Energy will add 3 GW renewable capacity in FY25, 5 GW in FY26, and 8 GW in FY27, targeting 60 GW by FY32.

Top risk FGD policy uncertainty

Government may stop issuing new FGD tenders; though NTPC is hedged via cost-plus mechanism, any change could impact project timelines.

View Risks →