Promise Tracker
0 delivered, 0 close, 3 missed.
View Promises →NTPC delivered a strong Q2 FY25 with standalone PAT of ₹4,649 crore, up 19.66% YoY, driven by higher generation and cost pass-through mechanisms.
✓ Verified against BSE filing
NTPC delivered a strong Q2 FY25 with standalone PAT of ₹4,649 crore, up 19.66% YoY, driven by higher generation and cost pass-through mechanisms. Revenue was slightly lower due to a decline in average coal prices, but operational efficiency remained robust with coal PLF at 76.31% vs national average of 70.63%. The company is aggressively expanding its renewable portfolio through NTPC Green Energy (NGEL), targeting 3 GW RE addition in FY25, 5 GW in FY26, and 8 GW in FY27, aiming for 60 GW by FY32. On thermal, 13.6 GW of new capacity is planned for award by FY27, with 8.8 GW already bid out. The NGEL IPO is on track for Q3. Key risks include potential policy changes on FGD installations and rising thermal project costs due to air-cooled condenser requirements.
एनटीपीसी ने दूसरी तिमाही में मजबूत प्रदर्शन किया। कंपनी का मुनाफा 4,649 करोड़ रुपये रहा, जो पिछले साल से 19.66% ज्यादा है। यह बढ़ोतरी ज्यादा बिजली उत्पादन और लागत वसूली के कारण हुई। कोयले की कीमतें गिरने से कमाई थोड़ी कम हुई, लेकिन बिजली संयंत्रों की क्षमता उपयोग दर 76.31% रही, जो देश के औसत 70.63% से बेहतर है। कंपनी हरित ऊर्जा में तेजी से विस्तार कर रही है। इस साल 3 गीगावॉट, अगले साल 5 गीगावॉट और उसके बाद 8 गीगावॉट नवीकरणीय ऊर्जा जोड़ने का लक्ष्य है। 2032 तक 60 गीगावॉट हासिल करना है। थर्मल पावर में भी 13.6 गीगावॉट की नई क्षमता जोड़ी जाएगी। एनजीईएल का आईपीओ इसी तिमाही में आने वाला है। जोखिमों में नीतिगत बदलाव और बढ़ती लागत शामिल है।
0 delivered, 0 close, 3 missed.
View Promises →FGD policy uncertainty
View Risks →Full transcript text is available on this route.
Read Transcript →NTPC's coal plant load factor outperformed the national average of 70.63% in H1 FY25.
Highest ever coal production in H1 FY25, up from 16.06 MMT in H1 FY24.
NTPC Green Energy plans to add 3 GW renewable capacity in FY25, 5 GW in FY26, and 8 GW in FY27.
11.16 GW thermal capacity under construction; additional 13.6 GW to be awarded by FY27.
8.8 GW already bid out (award by Dec 2024), balance 4.8 GW in next two months; total 13.6 GW thermal capacity to be awarded by FY27.
Draft red herring prospectus filed; IPO process on track for completion in Q3 FY25.
NTPC Green Energy will add 3 GW renewable capacity in FY25, 5 GW in FY26, and 8 GW in FY27, targeting 60 GW by FY32.
NTPC group coal production to increase from 40 MMT in FY25 to about 67 MMT by FY29.
10.4 GW to be tendered in FY25, 3.2 GW in FY26, 1.6 GW in FY27. Includes Sipat, Darlipali, Meja, etc.
DRHP filing post-June 2024; NTPC to remain holding company post-IPO.
Government may stop issuing new FGD tenders; though NTPC is hedged via cost-plus mechanism, any change could impact project timelines.
CapEx per MW for new thermal projects has risen beyond ₹12 crore due to mandatory air-cooled condensers and limited bidders.
Under-recovery increased to ₹495 crore in Q2 from ₹381 crore last year due to higher planned outages (6.12% vs 5.19%).
Some thermal projects (e.g., Gadarwara Stage-II) have only 68% PPA consent; balance expected in four months but could slip.
Commissioning of renewable projects slower than guided due to module import clearance delays and land acquisition issues.
INR 776 crores under-recovery in FY24 due to lower availability at Barh and Barauni plants; though management expects reduction.
Dividend from JVs and subsidiaries fell from INR 2,336 crores in FY23 to INR 1,630 crores in FY24 due to retained earnings for reinvestment.
Out of 15.2 GW planned, only 8 GW has PPAs signed; remaining 7 GW needs tie-up with states/ministry.
Mentioned in Q2 FY24, Q3 FY24, Q4 FY24
Commissioning of renewable projects slower than guided due to module import clearance delays and land acquisition issues.
Mentioned in Q2 FY24, Q3 FY24, Q4 FY24
10.4 GW to be tendered in FY25, 3.2 GW in FY26, 1.6 GW in FY27. Includes Sipat, Darlipali, Meja, etc.
Mentioned in Q2 FY24, Q3 FY24
Despite delays, management reiterated the target of 15 GW operational renewable capacity by FY26.
NTPC Green Energy will add 3 GW renewable capacity in FY25, 5 GW in FY26, and 8 GW in FY27, targeting 60 GW by FY32.
Government may stop issuing new FGD tenders; though NTPC is hedged via cost-plus mechanism, any change could impact project timelines.
View Risks →