Adani Enterprises Limited — Q2 FY26
Adani Enterprises reported H1 FY26 consolidated total income of INR 44,281 crore and EBITDA of INR 7,688 crore, with incubating businesses contributing over 70% of EBITDA (up fr...
✓ Verified against BSE filing
Indian management teams deliver on roughly 12% of specific earnings-call promises. A low score does not indicate dishonesty — it reflects how aspirational forward guidance typically is.
FY26 CapEx of INR 35,000 crore
Management maintained consolidated CapEx guidance of INR 35,000 crore for FY26, with airports (INR 10,000 crore), petchem (INR 9,000 crore), and roads (INR 6,200 crore) as major components.
Current-quarter commentary contains related risk or weakness, so the promise appears not to have been delivered yet.
heuristic_v1Navi Mumbai Airport operational by October 2025
Navi Mumbai Airport expected to receive operational clearances around October 2025, with ramp-up to capacity within six months.
Current-quarter commentary contains related risk or weakness, so the promise appears not to have been delivered yet.
heuristic_v1Ganga Expressway completion in H2 FY26
Greenfield Ganga Expressway project is 85% complete and expected to be completed in the second half of FY26, with EBITDA contribution from next fiscal year.
Current-quarter commentary contains related risk or weakness, so the promise appears not to have been delivered yet.
heuristic_v1