PositiveQ4-FY26 · 2026-05-15Back to quarter ↗

Risk intelligence

Material risks this quarter

Dubai project launch delay due to geopolitical tensions

The Dubai project is launch-ready but delayed due to the Middle East war; management cannot provide a timeline.

medium

Potential slowdown in luxury demand from geopolitical uncertainty

Footfalls have dropped 5-10% in the last month due to war uncertainty, though conversion rates remain stable.

medium

Supply chain disruptions and input cost inflation

Shortage of some imported finished goods (e.g., tiles) and labor due to elections may cause temporary cost pressures.

low