Acme Solar Holdings Limited — Q2 FY26

Acme Solar reported a stellar Q2 FY26 with revenue of 601 crore (up 104% YoY) and EBITDA of 534 crore (up 180% YoY), driven by capacity additions and operational efficiencies.

bullish high
Compare with...
Revenue ₹601 Cr +104%
EBITDA ₹534 Cr +180%
PAT ₹115 Cr
EBITDA Margin 89% +200bps
Duration 60 min
Read Time 1 min read

Financial stats pending filing verification

2-Minute Summary

✦ AI-Generated from Full Transcript

Acme Solar reported a stellar Q2 FY26 with revenue of 601 crore (up 104% YoY) and EBITDA of 534 crore (up 180% YoY), driven by capacity additions and operational efficiencies. EBITDA margin expanded to 89% from 87% last year, aided by lower costs and higher PLF. PAT stood at 115 crore with a margin of 19%. The company commissioned 378 MW of the 450 MW FY26 target, with the balance expected by January. It also won 720 MW of new projects, including a 50 MW FDRE with a private discom and 670 MW solar-plus-storage. Management guided for 1 GWh BESS commissioning from Q4 FY26, adding ~170 crore annual EBITDA. Key risks include PPA signing delays for awarded projects and transmission connectivity delays, though management expressed confidence in resolution.

Risks4 trackedTranscriptfull text
Research workspace

Focused Modules

!Risks 4 risks

Risk Intelligence

PPA signing delays for awarded projects

View Risks →
Transcript Full text

Call Transcript

Full transcript text is available on this route.

Read Transcript →

Quarter Snapshot

Operational capacity 2,918 MW
+378 MW YTD

Operational portfolio now stands at 2,918 MW, with 378 MW commissioned in FY26 so far.

Under construction portfolio 4.5 GW
+720 MW QoQ

Under construction portfolio expanded to 4.5 GW including 2.3 GW of signed PPAs.

CUF 24.1%
+190bps YoY

Capacity utilization factor improved to 24.1% from 22.2% last year, with plant and grid availability at 99%.

DSO 27 days
record low

Days sales outstanding dropped to a record low of 27 days, driven by higher central PPA share.

Fast read

Guidance and risk preview

Top guidance FY26 capacity commissioning target of 450 MW

Company is on track to commission 450 MW in FY26; 378 MW already commissioned, balance 72 MW expected by early January.

Top risk PPA signing delays for awarded projects

Out of 93 GW awarded in FY24-25, 42 GW PPAs are pending; Acme's projects with NTPC and SJVN face delays, though management is confident of signing.

View Risks →