PPA signing delays for awarded projects
View Risks →Acme Solar reported a stellar Q2 FY26 with revenue of 601 crore (up 104% YoY) and EBITDA of 534 crore (up 180% YoY), driven by capacity additions and operational efficiencies.
Financial stats pending filing verification
Acme Solar reported a stellar Q2 FY26 with revenue of 601 crore (up 104% YoY) and EBITDA of 534 crore (up 180% YoY), driven by capacity additions and operational efficiencies. EBITDA margin expanded to 89% from 87% last year, aided by lower costs and higher PLF. PAT stood at 115 crore with a margin of 19%. The company commissioned 378 MW of the 450 MW FY26 target, with the balance expected by January. It also won 720 MW of new projects, including a 50 MW FDRE with a private discom and 670 MW solar-plus-storage. Management guided for 1 GWh BESS commissioning from Q4 FY26, adding ~170 crore annual EBITDA. Key risks include PPA signing delays for awarded projects and transmission connectivity delays, though management expressed confidence in resolution.
एक्मे सोलर ने दूसरी तिमाही (जुलाई-सितंबर 2025) में शानदार प्रदर्शन किया। कंपनी की कमाई 601 करोड़ रुपये रही, जो पिछले साल से दोगुनी से भी ज्यादा है। मुनाफा 534 करोड़ रुपये रहा, जो पिछले साल से 180% ज्यादा है। यह बढ़ोतरी नए बिजली संयंत्र लगाने और कामकाज में सुधार से हुई। कंपनी का खर्च घटने और बिजली उत्पादन बढ़ने से मुनाफा मार्जिन 89% हो गया। शुद्ध मुनाफा 115 करोड़ रुपये रहा। कंपनी ने इस साल 450 मेगावाट बिजली क्षमता जोड़ने का लक्ष्य रखा है, जिसमें से 378 मेगावाट पूरा हो चुका है। साथ ही, 720 मेगावाट के नए प्रोजेक्ट जीते हैं। कंपनी अगले साल जनवरी से बैटरी स्टोरेज से भी कमाई शुरू करेगी, जिससे सालाना 170 करोड़ रुपये अतिरिक्त मुनाफा होगा। हालांकि, कुछ प्रोजेक्ट्स के कागजात और बिजली लाइनों में देरी का जोखिम है, लेकिन कंपनी को भरोसा है कि ये जल्द हल हो जाएंगे।
PPA signing delays for awarded projects
View Risks →Full transcript text is available on this route.
Read Transcript →Operational portfolio now stands at 2,918 MW, with 378 MW commissioned in FY26 so far.
Under construction portfolio expanded to 4.5 GW including 2.3 GW of signed PPAs.
Capacity utilization factor improved to 24.1% from 22.2% last year, with plant and grid availability at 99%.
Days sales outstanding dropped to a record low of 27 days, driven by higher central PPA share.
Company is on track to commission 450 MW in FY26; 378 MW already commissioned, balance 72 MW expected by early January.
Out of 93 GW awarded in FY24-25, 42 GW PPAs are pending; Acme's projects with NTPC and SJVN face delays, though management is confident of signing.