ConCallIQ
Go Pro
POWERGRID Energy 01 Aug 2025

Powergrid Ltd — Q1 FY26

PowerGrid reported Q1 FY26 consolidated total income of INR 11,444 crore, EBITDA of INR 9,527 crore, and PAT of INR 3,631 crore.

bullish high
Revenue ₹11,444 Cr
EBITDA ₹9,527 Cr
PAT ₹3,631 Cr -2%
EBITDA Margin
Duration
Read Time 1 min read

Financial stats pending filing verification

2-Minute Summary

✦ AI-Generated from Full Transcript

PowerGrid reported Q1 FY26 consolidated total income of INR 11,444 crore, EBITDA of INR 9,527 crore, and PAT of INR 3,631 crore. PAT declined ~2% YoY due to higher CSR spend (INR 70 crore) and JV losses. Standalone PAT grew 7% YoY to INR 3,653 crore. Capex in Q1 was INR 6,981 crore, up 51% YoY, with a full-year target of INR 28,000 crore. The company has a strong order book of INR 148,000 crore (NCT cost) and expects INR 22,000 crore capitalization in FY26. Management highlighted robust demand from India's 500 GW renewable target, with INR 5.5-6 lakh crore of transmission projects yet to be awarded. Key risks include right-of-way challenges and supply chain inflation for transformers and GIS equipment.

Key Numbers

Capex Q1 FY26 INR 6,981 crore
+51% YoY

Capital expenditure in Q1 FY26 increased from INR 4,615 crore in Q1 FY25.

Order Book (NCT cost) INR 148,000 crore
N/A

Projects in hand include TBCB (INR 99,000 cr), RTM (INR 9,000 cr), new RTM (INR 37,000 cr), and others.

System Availability 99.84%
+2bps YoY

Transmission system availability remains world-class, improving from 99.82% last year.

Outstanding Receivables INR 3,151 crore
-43% YoY

Receivables reduced significantly from INR 5,548 crore in Q1 FY25, indicating improved collections.

What Changed vs Last Quarter

Comparing Q1 FY26 vs Q4 FY25
1 new guidance1 dropped4 new risk4 risk resolved
NEW
50% electricity consumption from renewables by December 2025

PowerGrid targets to source half of its electricity needs from renewable sources by end of 2025.

UPDATED
FY26 Capex target of INR 28,000 crore

Management reiterated the full-year capex plan of INR 28,000 crore, with Q1 already achieving INR 6,981 crore.

UPDATED
FY26 capitalization target of INR 22,000 crore

The company expects to commission projects worth INR 22,000 crore in FY26, with quarterly targets of INR 3,000 cr (Q2), INR 7,000 cr (Q3), and INR 8,000 cr (Q4).

UPDATED
FY27 Capex plan of INR 35,000 crore and FY28 of INR 45,000 crore

Management provided a multi-year capex outlook, indicating a ramp-up in spending as the project pipeline materializes.

DROPPED
Dividend payout may reduce further

Management indicated dividend per share could reduce from INR 9 in FY25 due to higher CapEx requirements.

NEW RISK
Right-of-way challenges persist

ROW issues remain a significant bottleneck for transmission line commissioning, especially in Delhi and Haryana, despite new compensation guidelines.

NEW RISK
Supply chain inflation for key equipment

Transformer costs have doubled in seven years, and GIS bay costs have risen from INR 6 crore to INR 14-15 crore, impacting project costs.

NEW RISK
Leh HVDC project technology risk

The Leh HVDC project faces delays due to technology challenges at high altitude; an alternative AC solution may be costlier and unproven in India.

NEW RISK
Consolidated PAT decline due to JV losses

Consolidated PAT fell ~2% YoY partly due to INR 70 crore loss from joint venture ESL, which management did not elaborate on further.

RISK GONE
ROW-related project delays

ROW compensation policy changes and state-level adoption delays caused commissioning slippages in FY25; may persist.

RISK GONE
Lower TBCB pipeline in FY26

Current TBCB pipeline is only INR 45,000-46,000 crore, significantly lower than INR 92,000 crore won in FY25, which could slow order book growth.

RISK GONE
ROE compression from higher equity base

ROE dipped ~100bps YoY as net worth grew faster than profits; further dilution possible if CapEx ramp-up requires equity.

RISK GONE
RE demand slowdown impacting transmission needs

Weak power demand and delayed PPAs for RE projects could reduce urgency for new transmission lines, affecting long-term pipeline.

Management Guidance

G

FY26 Capex target of INR 28,000 crore

Management reiterated the full-year capex plan of INR 28,000 crore, with Q1 already achieving INR 6,981 crore.

Management guidance capex
G

FY26 capitalization target of INR 22,000 crore

The company expects to commission projects worth INR 22,000 crore in FY26, with quarterly targets of INR 3,000 cr (Q2), INR 7,000 cr (Q3), and INR 8,000 cr (Q4).

Management guidance growth
G

FY27 Capex plan of INR 35,000 crore and FY28 of INR 45,000 crore

Management provided a multi-year capex outlook, indicating a ramp-up in spending as the project pipeline materializes.

Management guidance capex
G

50% electricity consumption from renewables by December 2025

PowerGrid targets to source half of its electricity needs from renewable sources by end of 2025.

Management guidance ai_strategy

Key Risks

R

Right-of-way challenges persist

ROW issues remain a significant bottleneck for transmission line commissioning, especially in Delhi and Haryana, despite new compensation guidelines.

high · management_commentary
R

Supply chain inflation for key equipment

Transformer costs have doubled in seven years, and GIS bay costs have risen from INR 6 crore to INR 14-15 crore, impacting project costs.

high · management_commentary
R

Leh HVDC project technology risk

The Leh HVDC project faces delays due to technology challenges at high altitude; an alternative AC solution may be costlier and unproven in India.

medium · analyst_question
R

Consolidated PAT decline due to JV losses

Consolidated PAT fell ~2% YoY partly due to INR 70 crore loss from joint venture ESL, which management did not elaborate on further.

medium · data_observation

Notable Quotes

We are driving energy transition as per the mission of Government of India. We have used mission for redevelopment in India, which requires huge transmission system, and POWERGRID is one of the largest transmission system developers in India.
R. K. Tyagi · Chairman & Managing Director
ROW is a very big problem in India. Making a transmission line is very, very challenging.
R. K. Tyagi · Chairman & Managing Director
Supply cost is increasing now because demand is more if you consider transformer, if you consider GIS, if you consider breaker, if you consider maybe insulator or even tower parts also.
R. K. Tyagi · Chairman & Managing Director

Frequently Asked Questions

What was Powergrid's revenue in Q1 FY26?

Powergrid reported revenue of ₹11,444 Cr in Q1 FY26, representing a — change compared to the same quarter last year.

What guidance did Powergrid management give for FY27?

FY26 Capex target of INR 28,000 crore: Management reiterated the full-year capex plan of INR 28,000 crore, with Q1 already achieving INR 6,981 crore. FY26 capitalization target of INR 22,000 crore: The company expects to commission projects worth INR 22,000 crore in FY26, with quarterly targets of INR 3,000 cr (Q2), INR 7,000 cr (Q3), and INR 8,000 cr (Q4). FY27 Capex plan of INR 35,000 crore and FY28 of INR 45,000 crore: Management provided a multi-year capex outlook, indicating a ramp-up in spending as the project pipeline materializes. 50% electricity consumption from renewables by December 2025: PowerGrid targets to source half of its electricity needs from renewable sources by end of 2025.

What are the key risks for Powergrid in FY27?

Key risks include Right-of-way challenges persist — ROW issues remain a significant bottleneck for transmission line commissioning, especially in Delhi and Haryana, despite new compensation guidelines.; Supply chain inflation for key equipment — Transformer costs have doubled in seven years, and GIS bay costs have risen from INR 6 crore to INR 14-15 crore, impacting project costs.; Leh HVDC project technology risk — The Leh HVDC project faces delays due to technology challenges at high altitude; an alternative AC solution may be costlier and unproven in India.; Consolidated PAT decline due to JV losses — Consolidated PAT fell ~2% YoY partly due to INR 70 crore loss from joint venture ESL, which management did not elaborate on further..

Did Powergrid meet its previous quarter's guidance?

Of 1 tracked promise, management 0 met, 0 close, 1 missed.

Where can I read the full Powergrid Q1 FY26 concall transcript?

The full earnings conference call transcript or source release is available on the linked source material. This page provides an AI-generated summary with filing verification status shown on the financial stats.