Capital expenditure in Q1 FY26 increased from INR 4,615 crore in Q1 FY25.
Powergrid Ltd — Q1 FY26
PowerGrid reported Q1 FY26 consolidated total income of INR 11,444 crore, EBITDA of INR 9,527 crore, and PAT of INR 3,631 crore.
Financial stats pending filing verification
2-Minute Summary
PowerGrid reported Q1 FY26 consolidated total income of INR 11,444 crore, EBITDA of INR 9,527 crore, and PAT of INR 3,631 crore. PAT declined ~2% YoY due to higher CSR spend (INR 70 crore) and JV losses. Standalone PAT grew 7% YoY to INR 3,653 crore. Capex in Q1 was INR 6,981 crore, up 51% YoY, with a full-year target of INR 28,000 crore. The company has a strong order book of INR 148,000 crore (NCT cost) and expects INR 22,000 crore capitalization in FY26. Management highlighted robust demand from India's 500 GW renewable target, with INR 5.5-6 lakh crore of transmission projects yet to be awarded. Key risks include right-of-way challenges and supply chain inflation for transformers and GIS equipment.
पावरग्रिड ने पहली तिमाही में कुल कमाई 11,444 करोड़ रुपये दर्ज की। कंपनी का मुनाफा 3,631 करोड़ रुपये रहा, जो पिछले साल से 2% कम है। इसकी वजह सामाजिक जिम्मेदारी पर 70 करोड़ रुपये का अतिरिक्त खर्च और संयुक्त उद्यमों में घाटा है। अकेले कंपनी का मुनाफा 7% बढ़कर 3,653 करोड़ रुपये हो गया। कंपनी ने इस तिमाही में 6,981 करोड़ रुपये का निवेश किया, जो पिछले साल से 51% अधिक है। पूरे साल 28,000 करोड़ रुपये निवेश का लक्ष्य है। कंपनी के पास 1,48,000 करोड़ रुपये के ऑर्डर हैं। भारत के 500 गीगावॉट नवीकरणीय ऊर्जा लक्ष्य से बिजली ट्रांसमिशन की मांग बढ़ रही है। अभी 5.5-6 लाख करोड़ रुपये के प्रोजेक्ट बाकी हैं। मुख्य चुनौतियां जमीन अधिग्रहण और ट्रांसफॉर्मर व उपकरणों की बढ़ती कीमतें हैं।
Key Numbers
Projects in hand include TBCB (INR 99,000 cr), RTM (INR 9,000 cr), new RTM (INR 37,000 cr), and others.
Transmission system availability remains world-class, improving from 99.82% last year.
Receivables reduced significantly from INR 5,548 crore in Q1 FY25, indicating improved collections.
What Changed vs Last Quarter
PowerGrid targets to source half of its electricity needs from renewable sources by end of 2025.
Management reiterated the full-year capex plan of INR 28,000 crore, with Q1 already achieving INR 6,981 crore.
The company expects to commission projects worth INR 22,000 crore in FY26, with quarterly targets of INR 3,000 cr (Q2), INR 7,000 cr (Q3), and INR 8,000 cr (Q4).
Management provided a multi-year capex outlook, indicating a ramp-up in spending as the project pipeline materializes.
Management indicated dividend per share could reduce from INR 9 in FY25 due to higher CapEx requirements.
ROW issues remain a significant bottleneck for transmission line commissioning, especially in Delhi and Haryana, despite new compensation guidelines.
Transformer costs have doubled in seven years, and GIS bay costs have risen from INR 6 crore to INR 14-15 crore, impacting project costs.
The Leh HVDC project faces delays due to technology challenges at high altitude; an alternative AC solution may be costlier and unproven in India.
Consolidated PAT fell ~2% YoY partly due to INR 70 crore loss from joint venture ESL, which management did not elaborate on further.
ROW compensation policy changes and state-level adoption delays caused commissioning slippages in FY25; may persist.
Current TBCB pipeline is only INR 45,000-46,000 crore, significantly lower than INR 92,000 crore won in FY25, which could slow order book growth.
ROE dipped ~100bps YoY as net worth grew faster than profits; further dilution possible if CapEx ramp-up requires equity.
Weak power demand and delayed PPAs for RE projects could reduce urgency for new transmission lines, affecting long-term pipeline.
Management Guidance
FY26 Capex target of INR 28,000 crore
Management reiterated the full-year capex plan of INR 28,000 crore, with Q1 already achieving INR 6,981 crore.
Management guidance capexFY26 capitalization target of INR 22,000 crore
The company expects to commission projects worth INR 22,000 crore in FY26, with quarterly targets of INR 3,000 cr (Q2), INR 7,000 cr (Q3), and INR 8,000 cr (Q4).
Management guidance growthFY27 Capex plan of INR 35,000 crore and FY28 of INR 45,000 crore
Management provided a multi-year capex outlook, indicating a ramp-up in spending as the project pipeline materializes.
Management guidance capex50% electricity consumption from renewables by December 2025
PowerGrid targets to source half of its electricity needs from renewable sources by end of 2025.
Management guidance ai_strategyKey Risks
Right-of-way challenges persist
ROW issues remain a significant bottleneck for transmission line commissioning, especially in Delhi and Haryana, despite new compensation guidelines.
high · management_commentarySupply chain inflation for key equipment
Transformer costs have doubled in seven years, and GIS bay costs have risen from INR 6 crore to INR 14-15 crore, impacting project costs.
high · management_commentaryLeh HVDC project technology risk
The Leh HVDC project faces delays due to technology challenges at high altitude; an alternative AC solution may be costlier and unproven in India.
medium · analyst_questionConsolidated PAT decline due to JV losses
Consolidated PAT fell ~2% YoY partly due to INR 70 crore loss from joint venture ESL, which management did not elaborate on further.
medium · data_observationNotable Quotes
We are driving energy transition as per the mission of Government of India. We have used mission for redevelopment in India, which requires huge transmission system, and POWERGRID is one of the largest transmission system developers in India.
ROW is a very big problem in India. Making a transmission line is very, very challenging.
Supply cost is increasing now because demand is more if you consider transformer, if you consider GIS, if you consider breaker, if you consider maybe insulator or even tower parts also.
Frequently Asked Questions
What was Powergrid's revenue in Q1 FY26?
Powergrid reported revenue of ₹11,444 Cr in Q1 FY26, representing a — change compared to the same quarter last year.
What guidance did Powergrid management give for FY27?
FY26 Capex target of INR 28,000 crore: Management reiterated the full-year capex plan of INR 28,000 crore, with Q1 already achieving INR 6,981 crore. FY26 capitalization target of INR 22,000 crore: The company expects to commission projects worth INR 22,000 crore in FY26, with quarterly targets of INR 3,000 cr (Q2), INR 7,000 cr (Q3), and INR 8,000 cr (Q4). FY27 Capex plan of INR 35,000 crore and FY28 of INR 45,000 crore: Management provided a multi-year capex outlook, indicating a ramp-up in spending as the project pipeline materializes. 50% electricity consumption from renewables by December 2025: PowerGrid targets to source half of its electricity needs from renewable sources by end of 2025.
What are the key risks for Powergrid in FY27?
Key risks include Right-of-way challenges persist — ROW issues remain a significant bottleneck for transmission line commissioning, especially in Delhi and Haryana, despite new compensation guidelines.; Supply chain inflation for key equipment — Transformer costs have doubled in seven years, and GIS bay costs have risen from INR 6 crore to INR 14-15 crore, impacting project costs.; Leh HVDC project technology risk — The Leh HVDC project faces delays due to technology challenges at high altitude; an alternative AC solution may be costlier and unproven in India.; Consolidated PAT decline due to JV losses — Consolidated PAT fell ~2% YoY partly due to INR 70 crore loss from joint venture ESL, which management did not elaborate on further..
Did Powergrid meet its previous quarter's guidance?
Of 1 tracked promise, management 0 met, 0 close, 1 missed.
Where can I read the full Powergrid Q1 FY26 concall transcript?
The full earnings conference call transcript or source release is available on the linked source material. This page provides an AI-generated summary with filing verification status shown on the financial stats.