Topcon upgrade capex of ₹250-270 crore
Upgrading one 600 MW mono PERC line to topcon, increasing capacity to 750 MW, with commercial production targeted by Feb 2027.
Websol Energy System · forward-looking guidance across the available source record.
Guidance tracker
Upgrading one 600 MW mono PERC line to topcon, increasing capacity to 750 MW, with commercial production targeted by Feb 2027.
Phased expansion of 2 GW cell and module capacity, with land acquisition and funding structure under evaluation; management reaffirmed June 2027 timeline.
MOU signed with Linton for ingot and wafer technology; target to commission capacity before June 2028 to comply with domestic wafer mandate.
Management expects cell margins to stay healthy over next 2-3 years, supported by ALMM list 2 and government schemes, though silver price and pricing dynamics may cause fluctuations.