Major Maintenance Deferred to H2 FY27
Planned major maintenance works deferred from H1 to H2 FY27 due to uncertainty around bitumen availability and pricing arising from Middle East geopolitical tensions.
Vertis Infrastructure Trust · forward-looking guidance across the available source record.
Guidance tracker
Planned major maintenance works deferred from H1 to H2 FY27 due to uncertainty around bitumen availability and pricing arising from Middle East geopolitical tensions.
NHP has identified 16 assets aggregating 1,631 km potentially to be offered through TOT during FY27 under the multi-lane freeflow (MLF) model.
₹7 billion loan raised from international bank at competitive rate to refinance existing facilities, resulting in reduction of overall cost of debt by a few basis points.
NHP commenced pilot implementation of multi-lane freeflow at 25 toll plazas in FY26; actual performance data not yet available, financial implications remain to be assessed.
Management has commenced the public listing process for Vertis Infrastructure Trust but provided no specific timeline or target date for completion.
In response to elevated gas prices at Rs 80,000/tonne versus Rs 48,000 average, management is deferring major maintenance cycles by a few months until input costs normalize.
MLSS barrier pilot launched at Chyasi Plaza in May 2026; Vertis has implemented single-lane SLSS at one RST DBCP achieving 100% throughput increase, positioning for broader MLS adoption.