TRANSRAILL / language trends

Read confidence between the lines.

Transrail Lighting · tone and specificity signals across the available quarters.

Research layer active

Language signals

What changed in management language.

Q3-FY26 · Randhir Narang

We grew by 9% over last year in the same period of 9 months. Our L1 is around 3,500 crores and 15,000 crores we already bid. So we're looking at another 1,500 to 2,000. So we will better and beat our last year's order intake.

tracked

Q3-FY26 · Randhir Narang

We are not looking at minimizing our growth but there is a certain amount of we have some RO issues some forest issues in several projects in domestic and some issues on RO and international so we are giving you a conservative guidance and I said 27% plus so we are hopeful that we resolve that and we improve.

tracked

Q3-FY26 · Deepak Kandelwal

Our profit before tax for this 9 month has been 437 crores and whereas my cash flow from generation is more than 440 crores. So it is not 25 to 30%. It is substantially higher than that.

tracked

Q4-FY26 · Randip Narang

Revenue is not lost, it is postponed. That is the key question you should know in the EPC industry.

tracked

Q4-FY26 · Randip Narang

We have promised a level of 11.5 to 12% last year and we can't compare it to the previous year because the nature and type of projects is different. Today with the supply chain disruptions, delays, energy price increases, inflation we believe around 11% is a good number to go forward.

tracked

Q4-FY26 · Randip Narang

We have done very well. Phase one is completed. Phase 2 will get completed in the next 3-4 months and we are very confident on the execution piece. The Bangladesh project we will try to close in the next 6 months.

tracked