Regulatory disallowance of power purchase costs

₹171 cr provision booked in Q4; similar past disallowances were later reversed, but outcome uncertain.

medium

High LNG spot prices impacting merchant profitability

At current $16-20/MMBtu, merchant power sales are challenging; management noted difficulty in RTC market.

medium

Gas supply availability post-summer cargoes

After June, no contracted cargoes; reliance on spot market for availability demonstration, which may be costly.

high