TATAPOWER / guidance tracker

Keep management guidance in view.

Tata Power Company · forward-looking guidance across the available source record.

Research layer active

Guidance tracker

What management said would happen.

Renewable capacity target of 2.5-2.7 GW for FY27

200 MW already commissioned by June 30, another 500 MW expected within weeks, with balance capacity spread across subsequent quarters. Current portfolio at 6.7 GW will cross 9 GW by year-end.

expansion

Rooftop solar revenue growth of 60-70% in FY27

After doubling revenue to ₹4,800 crore in FY26, management expects continued strong growth of 60-70% driven by robust demand, channel partner expansion, and new battery storage offerings for residential and industrial segments.

growth

Q2 commissioning of 800-900 MW renewable capacity

Pipeline of sight for 500 MW nearly ready with commissioning expected in Q2. TBCB projects (Agra and Fatehgarh lines) will also get commissioned by October, enabling revenue recognition to start flowing.

expansion

Full-year capex of ₹25,000 crore with 50% execution visibility

Q2 capex expected at ₹6,000-6,500 crore as PSP work accelerates and renewable commissioning consumes significant capital. Capital allocation split between new projects with clear line of sight and existing T&D pipeline.

capex

FY27 Renewable Capacity Target: 2.5-3 GW (own projects only)

Third-party execution is largely complete; all new projects will serve own requirements. Pipeline of 5.2 GW to be executed over 2 years.

expansion

Solar Manufacturing EBITDA Margin: 28% for Q3, 20% for 9M

Manufacturing margins are expected to improve further as plant learning curve matures; not expected to deteriorate.

margins

Rooftop Solar: 50-60% more capacity addition expected YoY

Driven by government schemes including Ujala (utility-led) scheme in Odisha, and PM program adding 50 lakh houses to existing 25 lakh target.

growth

Mundra Plant Restart: Expected by end of February 2026

SPA agreed with Gujarat on all but one point; agreement will be circulated to other states for parallel discussions.

expansion

Capex of ₹25,000 crore in FY27

Management expects to spend ₹25,000 crore in FY27, including delayed projects from FY26.

capex

2.5 GW renewable capacity addition in FY27

Target to commission 2.5 GW of renewable capacity (solar, wind, hybrid) in FY27.

growth

Rooftop solar growth of 50-60% in FY27

Expects rooftop solar business to grow 50-60% in FY27, maintaining ~20% market share.

growth

Mundra SPA with four states in 4-6 weeks

Expects to finalize supplementary PPAs with remaining four states within 4-6 weeks.

other