Receivable days stretched to 93 days
Receivable days closed at 93 vs target of 80, partly due to RINL contract closure. Recovery expected in H1 FY27.
Tara Chand Infralogistic · Material risks, their source context, and severity in the latest available quarter.
ConCallIQ research layer
Use the controls below to narrow the view, then follow the evidence into the next layer of context.
Risk intelligence
Receivable days closed at 93 vs target of 80, partly due to RINL contract closure. Recovery expected in H1 FY27.
Q4 revenue missed target by ~₹10 crore due to project execution delays at client sites, deferred to Q1 FY27.
Analyst raised concern about potential margin dilution from Tarachand Metallics; management provided no concrete numbers.
Management cited forex volatility as a risk for new equipment purchases, though mitigated by annual purchase plans.