Material risks this quarter

Execution risk on large Hindustan Zinc order

The ₹300 Cr order from Hindustan Zinc is the largest ever; any delay in mobilization or execution could impact revenue visibility.

medium

Monsoon disruption to operations

Historically, monsoon affects drilling operations; management claims current order book mitigates this, but weather remains a risk.

medium

High receivables and working capital

Receivables are elevated (implied ~6 months credit), though management cites retention money and improving private client mix.

medium

Coal block development delays

The Jharkhand coal block requires regulatory approvals (mining plan); any delay could push back revenue generation from this vertical.

low