SOLARWORLD / guidance tracker

Keep management guidance in view.

Solarworld Energy Solutions · forward-looking guidance across the available source record.

Research layer active

Guidance tracker

What management said would happen.

FY26 Revenue: Target Rs 1,500 crore

Management expressed confidence in exceeding the previously stated Rs 1,500 crore revenue guidance for FY26, with Q4 expected to carry forward Q3's strong momentum.

revenue

BESS Project Operationalization: 12-13 Months

Both the RUVNL (200 MW/400 MWh) and GUVNL projects will become operational within 12-13 months, generating annuity revenue over 12 years.

expansion

Cell Line Commercialization: Dec 2026 - Jan 2027

1.2 GW solar cell manufacturing facility targeted for commercial operations between December 2026 and January 2027, enabling DCR-compliant panel manufacturing from June 2026 mandate.

expansion

FY27: 25-30% EPC Growth Expected

Management anticipates 25-30% growth in EPC segment for FY27 if market conditions sustain, driven by BESS-integrated and RTC projects replacing pure solar tenders.

growth

FY27 Revenue Target: ₹2,000 Crore

Management targets ~₹2,000 crore revenue in FY27, representing ~40–45% growth over FY26's ₹1,416 crore, driven by BESS revenue ramp-up (expected ₹800–1,000 crore from BESS) and sustained solar EPC execution.

revenue

FY27 PAT Margin Guidance: 8–11%

EPC margins guided in 8–11% range for FY27 depending on raw material price trajectory. Management noted Q1 FY27 is challenging due to elevated commodity prices (copper +40%, aluminum +50% vs. Oct 2025) and rupee depreciation (₹96/USD). Margins would improve if West Asia situation normalizes.

margins

BESS PAT Margin Target: 14–15%

Battery energy storage EPC business expected to deliver 14–15% PAT margins at full utilization. 3.4 GWh fully automated BESS manufacturing facility (with CUCAR robotics) is ready with trials underway; projected revenue potential ~₹3,300 crore at full capacity (740 containers/year at ₹4.5 crore each).

margins

Solar Cell Manufacturing: June 2027 Commercial Operation

1.2 GW solar cell manufacturing facility in Nagpur is under construction with approvals received; commercial operation targeted by June 2027, providing backward integration to meet ALMM2 requirements and reduce supply chain dependency.

expansion