SJVN / Q2-FY26 / risks

Keep the risk register visible.

SJVN · Material risks, their source context, and severity in the latest available quarter.

Research layer active

ConCallIQ research layer

Signal, with the source still visible.

Use the controls below to narrow the view, then follow the evidence into the next layer of context.

WatchQ2-FY26 · 2025-11-06Back to quarter ↗

Risk intelligence

Material risks this quarter

Transmission Connectivity Bottleneck Delaying RE Projects

Despite winning tenders for 13.74 GW and issuing LOAs, only 3.74 GW has signed PSAs/PPAs. Grid connectivity issues, transmission line shortages, and Supreme Court-related matters are blocking project commissioning, particularly in Rajasthan and Gujarat.

high

PPA/PSA Signing Uncertainty for Awarded Tenders

Stakeholder consultations underway with Ministry of Power, MNRE, and bidders on ~9-10 GW of awarded capacity awaiting PPA signing. Rebidding possibility remains; clarity expected in 2-3 months.

high

Revenue Pressure from Himalayan Floods

Nathpa Jhakri and Rampur plants faced shutdowns due to high silt and flood conditions in Himachal Pradesh, impacting plant availability factor and reducing capacity/energy charges by estimated INR 50-60 crore. This is recurring weather-related risk.

medium

Tax Benefit Expiry and Rising Finance Costs

Loss of Section 80-IA exemption (INR 52 crore impact) for a project that completed 10 years. Finance costs increased ~INR 50 crore YoY as projects move from CWIP to commissioned assets with associated debt servicing.

medium