Company profile / SJVN

SJVN earnings calls.

Other · 4 quarters tracked · source-linked performance, management guidance and promise context.

Research layer active
WatchCredibility 0/100Latest record q2-fy26

Latest revenue

₹1,032 Cr

verified financial record

Quarters tracked

4

source records in the directory

Delivery assessment

0

Across 7 tracked commitments: 0 delivered, 7 missed.

Call date

2025-11-06

latest available source date

Signal trajectory

4 actual quarters
Revenue (₹ Cr)PositiveWatchNegative
4 actual records
Actual quarterly Revenue (₹ Cr) trajectoryReported values plotted by quarter. Hover or focus a point for its quarter, value, and source sentiment.Q1 FY25: 870 · Positive source sentimentQ1 FY25Q2 FY25: 1,026 · Watch source sentimentQ2 FY25Q3 FY25: 671 · Positive source sentiment · 2025-01-29Q3 FY25Q2 FY26: 1,032 · Watch source sentiment · 2025-11-06Q2 FY261,032671
Values are taken from the available verified source records; sentiment color is a separate source-read indicator.

Current read

0/100

Across 7 tracked commitments: 0 delivered, 7 missed.

Latest source read

What changed this quarter?

Open quarter read

SJVN's Q2 FY26 call centered on operational milestones and project execution rather than financial performance. Unit 1 of the 1,320 MW Buxar Thermal Power Project achieved COD in early November, with Unit 2 expected by January-February 2026. The 680 MW Bikaner Solar Project reached COD under the CPSU scheme. Management flagged revenue pressure from flood-related plant availability issues at Himalayan hydel stations (Nathpa Jhakri and Rampur), loss of the Section 80-IA tax benefit (INR 52 crore), and increased finance costs (up INR 50 crore YoY) weighing on profitability. Depreciation rose to INR 170 crore from INR 132 crore due to new commissioned assets. Total installed capacity stands at 3,146.52 MW with 5,091 MW under construction across hydro, thermal, and solar projects. As a Renewable Energy Implementing Agency, SJVN has tendered 19.8 GW, with LOAs for 13.74 GW but only 3.74 GW in signed PSAs/PPAs—grid connectivity delays are the primary bottleneck. H1 CapEx of INR 3,600 crore against full-year target of INR 7,500 crore was reported. Near-term capacity additions of ~650 MW expected this fiscal year should support revenue recovery.

Colored figures compare against the previous available record. Hover or focus one for the comparison.

Signal

Watch

Revenue

₹1,032 Cr

Source date

2025-11-06

Across the record

Quarter history.

4 source records

History modules

Follow the numbers and themes.