Material risks this quarter

Steel Sector Cyclical Weakness

Steel prices rangebound at lower levels due to seasonal factors and imports; anti-dumping duties lifted on certain products from China, Vietnam, Korea in October 2025.

medium

Indonesia Coal Mine Land Acquisition Delays

The Indonesia coal mine (targeting 1.88MTPA) faces challenges in land acquisition due to plasma plantation of rubber and palm oil, with flooding risks from heavy rains. Expansion is dependent on government intervention for surface rights acquisition.

medium

Supreme Court Case Timeline Uncertainty

While management asserts no material hurdles, the SKS power case has seen multiple hearing date shifts. Next hearing scheduled for November 18, 2025, and the legal process continues to take its own time, creating uncertainty around final resolution.

medium

ITP Expansion Approval Dependency

The proposed ITP thermal power expansion (600-800MW configuration under study) is contingent on obtaining forest clearance and other regulatory approvals before construction can commence on the ground, beyond just DPR finalization.