Risk intelligence

Material risks this quarter

Working capital stress

Working capital days extended to 73 days versus historical 50-55 days due to delayed payments (~8 days impact) and early creditor payments for vendor incentives. This drove higher interest costs and cash deployment.

medium

Large deal ROCE deterioration

Management acknowledged that competition has intensified in AI data center deals with lower ROCE than first-mover NMDC project. Despite multiple pipeline opportunities in Q2-Q4, they are selectively evaluating each deal for profitability.

medium

Inventory obsolescence exposure

An analyst (Atria Pal) raised concerns about ₹400 crore disputed tax claim as contingent liability and inventory risk. Management downplayed tax risk but acknowledged provisioning for inventories held over 1-2 years as prudent accounting practice.

medium

Gradual Windows refresh adoption

Despite industry excitement around Windows 10 end-of-support in October 2025, management admitted India's adoption speed is slower than developed markets—refresh cycle will be gradual starting H2 rather than immediate surge.