Material risks this quarter

CERC draft regulations on O&M and ROE

Draft regulations propose changes to O&M norms and reduce ROE to 15% for new assets. Management expects minimal impact but discussions ongoing.

medium

Supply chain constraints for transformers and GIS

Management acknowledged potential challenges in transformer and GIS supply, but noted government actions to develop more vendors.

medium

Aggressive ISTS CAPEX target may face execution delays

Analyst flagged that the INR 310,000 crore ISTS target over FY22-27 appears aggressive given the need for rapid awarding and execution.

medium

Leh-Ladakh HVDC project timeline risk

The project has a long gestation of ~5 years from order placement, with commissioning expected only by FY2030, posing execution risk.

low