Material risks this quarter

Right-of-way challenges persist

ROW issues remain a significant bottleneck for transmission line commissioning, especially in Delhi and Haryana, despite new compensation guidelines.

high

Supply chain inflation for key equipment

Transformer costs have doubled in seven years, and GIS bay costs have risen from INR 6 crore to INR 14-15 crore, impacting project costs.

high

Leh HVDC project technology risk

The Leh HVDC project faces delays due to technology challenges at high altitude; an alternative AC solution may be costlier and unproven in India.

medium

Consolidated PAT decline due to JV losses

Consolidated PAT fell ~2% YoY partly due to INR 70 crore loss from joint venture ESL, which management did not elaborate on further.

medium