Right-of-way challenges persist
ROW issues remain a significant bottleneck for transmission line commissioning, especially in Delhi and Haryana, despite new compensation guidelines.
Powergrid · Material risks, their source context, and severity in the latest available quarter.
ConCallIQ research layer
Use the controls below to narrow the view, then follow the evidence into the next layer of context.
Risk intelligence
ROW issues remain a significant bottleneck for transmission line commissioning, especially in Delhi and Haryana, despite new compensation guidelines.
Transformer costs have doubled in seven years, and GIS bay costs have risen from INR 6 crore to INR 14-15 crore, impacting project costs.
The Leh HVDC project faces delays due to technology challenges at high altitude; an alternative AC solution may be costlier and unproven in India.
Consolidated PAT fell ~2% YoY partly due to INR 70 crore loss from joint venture ESL, which management did not elaborate on further.