PositiveQ3-FY26 · 2026-01-27Back to quarter ↗

Risk intelligence

Material risks this quarter

UoP receivables collection delay

₹49 cr UoP charge for CY22 due by Dec 2025 but not yet received; bank guarantees valid till March 2026.

medium

Gopalpur terminal environmental clearance pending

Ministry of Environment sought clarifications; positive outcome expected but timeline uncertain.

medium

Long-term contract renewal negotiations

Renewal of 7.5 MTPA capacity agreements with GSPC, IOC, BPCL under discussion; commercial terms undisclosed.

medium

LNG price sensitivity for power sector

Power sector demand materializes only at LNG prices around $7-8/mmBtu; current prices may not sustain.

high