PETRONETLNG / guidance tracker

Keep management guidance in view.

Petronet LNG · forward-looking guidance across the available source record.

Research layer active

Guidance tracker

What management said would happen.

Dahej expansion mechanical completion by March 2026

The 5 MTPA capacity expansion at Dahej (to 22.5 MTPA) will be mechanically completed by end of FY26.

expansion

Kochi-Bangalore pipeline connectivity by June 2026

Pipeline connecting Kochi terminal to national grid expected by June 2026, enabling access to CGD markets.

expansion

FY27 total capex of ₹9,000 cr

Includes ₹7,500 cr for petchem, ₹800 cr for third jetty, and balance for other projects.

capex

Dividend payout maintained at 40-50%

Despite large capex, management expects to maintain healthy dividend payout ratio.

other

Capex of ₹9,000 crore for FY27

Major spend of ~₹7,500 crore on petrochemical project, ₹600 crore on third jetty, ₹300-400 crore on Gopalpur terminal, and ₹70 crore on Kochi small-scale LNG plant.

capex

Qatar supply resumption by June 2026

Management expects Qatar Energy to resume supplies within 3-4 weeks after the Gulf conflict ends, potentially from first week of June.

growth

Dividend maintained at ₹3 per share for FY26

Board recommended final dividend of ₹3 per share; management aims to maintain absolute dividend level despite capex.

other