Dahej expansion mechanical completion by March 2026
The 5 MTPA capacity expansion at Dahej (to 22.5 MTPA) will be mechanically completed by end of FY26.
Petronet LNG · forward-looking guidance across the available source record.
Guidance tracker
The 5 MTPA capacity expansion at Dahej (to 22.5 MTPA) will be mechanically completed by end of FY26.
Pipeline connecting Kochi terminal to national grid expected by June 2026, enabling access to CGD markets.
Includes ₹7,500 cr for petchem, ₹800 cr for third jetty, and balance for other projects.
Despite large capex, management expects to maintain healthy dividend payout ratio.
Major spend of ~₹7,500 crore on petrochemical project, ₹600 crore on third jetty, ₹300-400 crore on Gopalpur terminal, and ₹70 crore on Kochi small-scale LNG plant.
Management expects Qatar Energy to resume supplies within 3-4 weeks after the Gulf conflict ends, potentially from first week of June.
Board recommended final dividend of ₹3 per share; management aims to maintain absolute dividend level despite capex.