Slower ramp-up of KG 98/2 due to weather
Management cited rough weather as a cause for slower production ramp-up; further delays could impact production targets.
Ongc · Material risks, their source context, and severity in the latest available quarter.
ConCallIQ research layer
Use the controls below to narrow the view, then follow the evidence into the next layer of context.
Risk intelligence
Management cited rough weather as a cause for slower production ramp-up; further delays could impact production targets.
Analyst raised concern about windfall tax on KG Basin oil; management stated they do not anticipate it currently, but uncertainty remains.
TotalEnergies' Mozambique LNG project faces delays due to elections; OVL's CapEx may increase once force majeure is lifted.
OPaL reported PAT loss of INR 983 crore in Q1 FY25; restructuring awaits government clearance, posing downside risk.