WatchQ1-FY25 · 2024-08-05Back to quarter ↗

Risk intelligence

Material risks this quarter

Slower ramp-up of KG 98/2 due to weather

Management cited rough weather as a cause for slower production ramp-up; further delays could impact production targets.

medium

Windfall tax applicability on KG Basin oil

Analyst raised concern about windfall tax on KG Basin oil; management stated they do not anticipate it currently, but uncertainty remains.

medium

Mozambique project delays

TotalEnergies' Mozambique LNG project faces delays due to elections; OVL's CapEx may increase once force majeure is lifted.

medium

OPaL losses continue

OPaL reported PAT loss of INR 983 crore in Q1 FY25; restructuring awaits government clearance, posing downside risk.