Risk intelligence

Material risks this quarter

Renewable project execution delays

Land and transmission connectivity remain key challenges; management acknowledged connectivity may become available only by FY29-30.

medium

Thermal project slippages at Obra and Anpara

These projects are on hold due to coal availability and water issues, potentially impacting thermal capacity addition targets.

medium

PPA status uncertainty for renewable pipeline

Management did not provide a clear breakdown of PPA coverage for the 17 GW pipeline, leaving revenue visibility unclear.

medium

Chhabra plant acquisition delays

Discussions on modalities and coal arrangements are still ongoing; no timeline for completion was provided.

low