WatchQ3-FY26 · 2026-01-30Back to quarter ↗

Risk intelligence

Material risks this quarter

Curtailment losses in renewables

NGEL lost 420 MU and Ayana lost 212 MU due to grid curtailment in 9M FY26, impacting generation and profitability.

high

Delays in thermal project awards

Meja and Lara thermal awards are delayed due to approval processes and contractor extensions, pushing timelines.

medium

Aggressive green ammonia bid

The SECI green ammonia bid won by NGEL appears aggressive on pricing, though management claims healthy IRR.

medium

Fixed cost under-recovery

Fixed cost under-recovery stood at INR 454 crore as of December 2025, though efforts are being made to reduce it.

medium