Bangladesh plant shutdown

BIFPCL plant shut due to coal and dollar shortage; INR 1,324 Cr equity at risk.

high

Execution delays in thermal projects

BHEL-related delays in commissioning of Patratu and North Karanpura units; management expressed optimism but risks remain.

medium

Renewable capacity addition back-ended

Only 640 MW added in 9M FY25 vs 3,088 MW target; heavy reliance on Q4 execution.

medium