NTPC / Q2-FY25 / risks

Keep the risk register visible.

Ntpc · Material risks, their source context, and severity in the latest available quarter.

Research layer active

ConCallIQ research layer

Signal, with the source still visible.

Use the controls below to narrow the view, then follow the evidence into the next layer of context.

PositiveQ2-FY25 · 2024-10-30Back to quarter ↗

Risk intelligence

Material risks this quarter

FGD policy uncertainty

Government may stop issuing new FGD tenders; though NTPC is hedged via cost-plus mechanism, any change could impact project timelines.

medium

Rising thermal project costs

CapEx per MW for new thermal projects has risen beyond ₹12 crore due to mandatory air-cooled condensers and limited bidders.

medium

Under-recovery from disincentives

Under-recovery increased to ₹495 crore in Q2 from ₹381 crore last year due to higher planned outages (6.12% vs 5.19%).

low

PPA signing delays for thermal projects

Some thermal projects (e.g., Gadarwara Stage-II) have only 68% PPA consent; balance expected in four months but could slip.

medium