PositiveQ4-FY26 · 2026-05-15Back to quarter ↗

Risk intelligence

Material risks this quarter

Government payment delays

Management noted that government payments have slowed, with March collections lower than expected, impacting working capital.

medium

Raw material price inflation

Steel prices have risen significantly; management has raised prices and uses escalation clauses but impact on margins remains uncertain.

medium

Goodwill impairment and asset spike unexplained

A 7 crore goodwill impairment and 17x increase in other current assets were noted but management could not explain them on the call.

low

Capacity bottleneck before new plant

Current capacity is limited to ~150-160 crore revenue; management is outsourcing and adding temporary capacity, but execution risk remains.

medium