Material risks this quarter

Slippage in large order closures

Management noted that large orders in Q4 pipeline could slip to subsequent quarters, impacting order inflow guidance.

medium

Margin pressure from fixed-price contracts

45% of order book is fixed-price; cost overruns or delays could compress margins, especially in hydrocarbon and thermal projects.

medium

Geopolitical risks in Middle East

Despite ceasefire, potential trade wars and regional instability could impact project execution and payment flows.

low

Execution challenges in domestic infrastructure

Delayed payments in water projects under Jal Jeevan Mission led to temporary execution slowdown; recovery depends on fund flow.