HINDZINC / Q3-FY26 / promises

Measure what management said.

Hindustan Zinc · A quarter-by-quarter view of forward statements and whether delivery is visible yet.

Research layer active

ConCallIQ research layer

Signal, with the source still visible.

Use the controls below to narrow the view, then follow the evidence into the next layer of context.

PositiveQ3-FY26 · 2026-01-20Back to quarter ↗

Management delivery ledger

Promises over time.

13 tracked

Q2-FY24 · Q1 FY24

Alloy plant, Rajpura Dariba mill, and fumer plant commissioning in Q2 FY24

Current-quarter commentary contains related risk or weakness, so the promise appears not to have been delivered yet.

missed

heuristic_v1

Q2-FY25 · Q1 FY25

160kt roaster commissioning preponed to Q3 FY25

Current-quarter commentary contains related risk or weakness, so the promise appears not to have been delivered yet.

missed

heuristic_v1

Q2-FY26 · Q1 FY26

Zinc COP to reach $1,000/ton

Current-quarter commentary contains related risk or weakness, so the promise appears not to have been delivered yet.

missed

heuristic_v1

Q3-FY25 · Q2 FY25

FY25 refined metal production guidance maintained at 1.2mt

Current-quarter commentary contains related risk or weakness, so the promise appears not to have been delivered yet.

missed

heuristic_v1

Q3-FY25 · Q2 FY25

FY25 cost of production guidance maintained at $1,050-1,100/ton

Current-quarter commentary contains related risk or weakness, so the promise appears not to have been delivered yet.

missed

heuristic_v1

Q3-FY26 · Q2 FY26

Growth capex guidance of $350-400 million for FY26

Current-quarter commentary contains related risk or weakness, so the promise appears not to have been delivered yet.

missed

heuristic_v1

Q4-FY24 · Q3 FY24

FY24 volume guidance reaffirmed

Current-quarter commentary contains related risk or weakness, so the promise appears not to have been delivered yet.

missed

heuristic_v1

Q4-FY24 · Q3 FY24

COP to be at lower end of $1,125-1,175/ton guidance

Current-quarter commentary contains related risk or weakness, so the promise appears not to have been delivered yet.

missed

heuristic_v1

Q4-FY24 · Q3 FY24

Silver production to exceed FY24 guidance

Current-quarter commentary contains related risk or weakness, so the promise appears not to have been delivered yet.

missed

heuristic_v1

Q4-FY25 · Q3 FY25

Full-year mine metal and refined metal production guidance maintained

Current-quarter results and commentary indicate the prior promise was delivered or materially on track.

met

heuristic_v1

Q4-FY25 · Q3 FY25

Cost of production guidance maintained at $1,050-1,100/ton, trending to lower band

Current-quarter results and commentary indicate the prior promise was delivered or materially on track.

met

heuristic_v1

Q4-FY26 · Q3 FY26

FY2026 silver production guidance maintained at 680 ± 10 tons

Current-quarter commentary contains related risk or weakness, so the promise appears not to have been delivered yet.

missed

heuristic_v1

Q4-FY26 · Q3 FY26

Growth capex of ~$300 million for FY2026

Current-quarter commentary contains related risk or weakness, so the promise appears not to have been delivered yet.

missed

heuristic_v1