GPPL / guidance tracker

Keep management guidance in view.

Gujarat Pipavav Port · forward-looking guidance across the available source record.

Research layer active

Guidance tracker

What management said would happen.

Tariff hike of 5% effective Jan 2026

A 5% tariff increase across container and marine services, expected to flow through as 3-4% revenue uplift.

revenue

Liquid jetty commissioning by December 2026

The new liquid jetty with 3.2 MMT capacity is on track for commissioning by December 2026.

capex

RoRo staging area expansion by June 2026

A 60,000 sqm expansion of RoRo staging area, with 30,000 sqm by March and remaining by May-June 2026, increasing car handling capacity to 400-450k cars.

expansion

KGP pipeline connectivity by March-June 2026

The Kalyan-Gandhar-Pipavav pipeline is expected to connect to the port between March and June 2026.

growth