ANML melt project completion by July 2027
The 163,000 MT ANML melt project is expected to be completed by July 2027, with upstream and downstream timing aligned.
Gujarat Narmada Valley Fertilizers and Chemicals · forward-looking guidance across the available source record.
Guidance tracker
The 163,000 MT ANML melt project is expected to be completed by July 2027, with upstream and downstream timing aligned.
McKinsey has been appointed for phase two to realize cost savings of a couple of hundred crore rupees on an annual basis, expected to flow to P&L over 12 months.
Management expects favorable revision in fixed cost and energy norms for urea, which could substantially reduce fertilizer segment losses.
Management is confident of achieving 67,000 MT TDI production for the full year, with H2 covering the Q2 deficit.
The captive power plant project is expected to be commissioned by end of March or early April 2026, generating net contribution of INR 82 crore annually.
The weak nitric acid project has a slight delay but critical path activities are unaffected; commissioning expected by June 2027.
Out of INR 260-300 crore annual savings target, only INR 5-7 crore from renewable power is locked; rest under negotiation.
No planned maintenance shutdown in Q4 FY26; next major annual shutdown is planned in Q2 FY27.