Risk intelligence

Material risks this quarter

Commodity Price Volatility

Steel prices have risen 4-5% recently; fixed-price contracts could pressure margins if prices spike sharply.

medium

Execution Delays from Customer Side

Prolonged monsoon and NGT ban in Delhi NCR delayed civil works, impacting Q3 revenue by ₹35-40 crore.

medium

Working Capital Stretch

Working capital days increased from 23 in Q2 to 38 in Q3 due to receivable stretch; management expects normalization to 35 days.

low

Capex Delay at Rajasthan Plant

Sandwich panel line expansion in Rajasthan delayed due to NGT ban; now expected commercial production in Q3 FY27.