PEC gas leakage incident may delay revenue ramp-up
A gas leakage at the PEC site caused a temporary well shutdown; management expects a 2-3 month delay in revenue ramp-up from this contract.
Deepak Builders & Engineers India · Material risks, their source context, and severity in the latest available quarter.
ConCallIQ research layer
Use the controls below to narrow the view, then follow the evidence into the next layer of context.
Risk intelligence
A gas leakage at the PEC site caused a temporary well shutdown; management expects a 2-3 month delay in revenue ramp-up from this contract.
Kandla Energy still has ~₹28 crore doubtful receivables; management did not rule out future provisioning, though none expected this year.
Major clients like ONGC and GAIL account for a large share of revenue; management acknowledged difficulty in diversifying away quickly.
New rigs from China are being deployed; any delays or operational issues could impact Q4 revenue expectations.