PEC gas leakage incident may delay revenue ramp-up

A gas leakage at the PEC site caused a temporary well shutdown; management expects a 2-3 month delay in revenue ramp-up from this contract.

medium

Potential further write-offs from Kandla Energy receivables

Kandla Energy still has ~₹28 crore doubtful receivables; management did not rule out future provisioning, though none expected this year.

medium

Client concentration risk with PSUs

Major clients like ONGC and GAIL account for a large share of revenue; management acknowledged difficulty in diversifying away quickly.

medium

Execution risk from new rig deployments

New rigs from China are being deployed; any delays or operational issues could impact Q4 revenue expectations.