Land acquisition delays at MCL
MCL's Basundhara coal field faced a 26-day stoppage due to land compensation disputes, impacting production.
Coalindia · Material risks, their source context, and severity in the latest available quarter.
ConCallIQ research layer
Use the controls below to narrow the view, then follow the evidence into the next layer of context.
Risk intelligence
MCL's Basundhara coal field faced a 26-day stoppage due to land compensation disputes, impacting production.
Management acknowledged daily rake shortages of 5 rakes in SECL and MCL, constraining dispatches.
E-auction premiums have been volatile, ranging from 50-60% to 90%, dependent on demand and import prices.
Management ruled out any FSA price hike for the power sector in the next 7-8 months, limiting revenue growth.