What management said would happen.

Sustained high capacity utilization

Management expects to maintain ~111% capacity utilization in H1 FY27, with a scheduled maintenance turnaround around Sep-Oct 2027.

growth

LOBS project capex of ₹1,600 crore

Group II and III LOBS project with all approvals in place; execution started, expected to complete over 2-3 years.

capex

Retail outlet rollout of ₹400 crore

300 retail outlet licenses taken; commissioning expected in FY27.

expansion

Normal maintenance capex of ~₹500 crore per annum

Includes low-cost debottlenecking and energy efficiency projects.