TAN plant commissioning by April 30, 2026
The TAN project is 92% complete and on track for completion by April 30, 2026, with management expecting 75-80%+ utilization in FY27.
Chambal Fertilisers and · forward-looking guidance across the available source record.
Guidance tracker
The TAN project is 92% complete and on track for completion by April 30, 2026, with management expecting 75-80%+ utilization in FY27.
Management guided for 12 new crop protection chemicals products and one specialty nutrient product to be launched in FY27.
The joint venture in Morocco is increasing P2O5 production capacity from 5 lakh MT to 7 lakh MT, expected by December 2026.
Sulfuric acid capacity in the Morocco JV is being increased, expected to be implemented a year ahead, in FY27.
Management expects to reach 75-80% utilization in the first year of operations, with production of ~170,000 tons over 9 months.
Management is ready to invest ₹9,500-10,000 crore in a new urea plant, pending government policy. Land, water, and environmental clearances are in place.
Total capex for FY27 estimated at ~₹500 crore, comprising ₹170-180 crore routine capex and balance for TAN project completion.
Strategic purchases made early in the year ensure raw material availability for complex fertilizers through July-August 2026.