Material risks this quarter

Construction disruption at Powai impacting occupancy

Ongoing construction at Signis 2 Powai is causing temporary occupancy loss at nearby hotel due to noise and dust; expected to stabilize over next two quarters.

medium

Delhi airport hotel timeline delays

Revised timeline for Delhi airport hotel due to pollution-related stoppages; partial launch now expected by Q4 FY27 instead of earlier.

medium

Margin dilution from leisure portfolio

Leisure assets like Aiva Kandala operate at lower margins than business hotels, potentially diluting overall EBITDA margins.

medium

Goa project approval delays

South Goa hotel project delayed due to dissolution of local CRZ committee; critical approval pending, pushing construction start.

medium