Double capacity to 2,000 looms by March 2028
Management plans to increase total looms from 1,000 to 2,000 over two years, with 160 looms already initiated in Unit 4B.
Borana Weaves · forward-looking guidance across the available source record.
Guidance tracker
Management plans to increase total looms from 1,000 to 2,000 over two years, with 160 looms already initiated in Unit 4B.
Total investment for doubling capacity estimated at ₹350-400 crore, funded through internal accruals and debt, with no equity dilution planned.
Rooftop solar (3.54 MW) to be commissioned by Feb 2026, wind-solar hybrid (19.79 MW) by May 2026, targeting annual savings of ₹18-20 crore.
Management expects margins to increase quarter-on-quarter from current 24.32%, aided by lower raw material costs post-removal of BIS restrictions.