BANSALWIRE / Q3-FY26 / claim-ledger

Audit the questions that mattered.

Bansal Wire Industries · Analyst questions, management answers, and the quality of the response where the ledger is available.

Research layer active

ConCallIQ research layer

Signal, with the source still visible.

Use the controls below to narrow the view, then follow the evidence into the next layer of context.

PositiveQ3-FY26 · 2026-02-10Back to quarter ↗

Questions audited

11

Answered directly

82%

Numeric claims

1

Consistency

contradicted

Question ledger

What was answered, and how?

Kunal Sharma · Vertors Research and Advisers

partial

Status of GST notice of ~206 cr and financial impact

actually we have already intimated the stock exchange now Everything has been sorted out and there is no demand right now and a little bit demand little bit demand is there and we have already filed appeal to the higher authority

Kunal Sharma · Vertors Research and Advisers

direct

Details on IHT product approval, volume, and quantum

We started this product in Q3. We've already received some customer approvals and this month we are looking at maybe a 20% capacity utilization. Our revised target for this year is to reach about 40% capacity utilization.

Kunal Sharma · Vertors Research and Advisers

direct

Why EBITDA growth not reflecting in PAT despite 20% growth

In the last quarter we have capitalized all interest cost we have capitalized all investments. Therefore you see a jump in depreciation as well as interest. Although our cash profit has increased by 15-20%. But PAT level does not reflect that because of higher depreciation.

Vinit · Invest

evasive

EBITDA growth guidance closer to 25% given stable per-ton EBITDA

That was in fact our target for Q3 but Q3 has not although we have shown good results in Q3 but it could still have been better because of October November we lost some volumes because of labor shortages. I would like to stick with my guidance.

Vinit · Invest

direct

Cash flow outlook for FY27 and drivers

For the next year our target was 350 crores. I think that is still intact. Looking at what we did in this year we should be able to achieve that easily as well. This will come from a lot of discounting and other provisions.

Vinit · Invest

direct

Update on steel cord approvals and timelines

We are behind by a month because of some approvals that we've now received from the insurance companies to start production. But other than that I see no major change there. Q2 Q3 is our target still for starting supplies of steel cord.

Adit Pal · MSA Capital Partners

direct

Update on consolidation of related party entities Balaji Wires and Bansal High Tensile

There are two parts to this consolidation. First on financials that has been consolidated last year. The only thing that is left right now is that there is still some production happening in those two entities in the older plants. But that is only being done for Bansal.

HA · Dalal and Brocha

partial

Asset turnover comparison between low carbon and high carbon categories

I do not have numbers of asset turn of each category right now but yes low carbon even though it is a lower EBITDA per ton business the asset turns are generally better. Low carbon asset turnover would be about two to two and a half times of our general high carbon portfolio.

Parts (Paras) · Anandrati

direct

Plans for older facilities after capacity moves to Dadri

These are two very unviable and very old facilities. Right now we are only running it just to service the market because we don't want to lose our customers. As and when we are able to shift our capacities, I think this will just shut down.

Parts (Paras) · Anandrati

direct

Expected losses from fire and insurance claim status

We have already posted an exceptional loss of 1.5 cr that was due to the inventory loss in the fire which we've estimated. Everything else was insured. We do not expect anything material to happen in Q4 as well.

Parts (Paras) · Anandrati

direct

Capacity breakdown by product and roadmap for FY27-28

Right now out of our capacity of 6 lakh 20,000 tons I would say about 55-60% is low carbon, 20% would be stainless steel and the rest will be high carbon. Going forward also we are looking at similar numbers.

Kunal Sharma · Vertors Research and Advisers

direct

Status of Sanand facility and backward integration plan

Beadwire we've already started and this was planned for the Dadri facility not in the Sanand plant. In Sanand it is more low carbon and stainless steel. 50% of the land was for backward integration, 50% for wire. We are utilizing that 50% as of now.