Project execution delays due to land acquisition and forest clearances
Two Maharashtra projects are stalled pending forest and land clearances, with potential start pushed to December or March.
Ashoka Buildcon · Material risks, their source context, and severity in the latest available quarter.
ConCallIQ research layer
Use the controls below to narrow the view, then follow the evidence into the next layer of context.
Risk intelligence
Two Maharashtra projects are stalled pending forest and land clearances, with potential start pushed to December or March.
Monetization of four HAM assets by March and two by June may slip if approvals or investor due diligence are delayed.
The ₹700 crore contingent consideration from BOT asset sales could be reduced to ~₹500 crore due to NHI claim uncertainties.
One MSRDC project (₹279 crore) was cancelled due to scope changes; similar issues could affect other packages.