Ashoka Buildcon · risk themes across the available quarters.

Research layer active

Bear-case history

Risks carried through the record.

Project execution delays due to land acquisition and forest clearances

Two Maharashtra projects are stalled pending forest and land clearances, with potential start pushed to December or March.

high

Slower-than-expected HAM asset monetization

Monetization of four HAM assets by March and two by June may slip if approvals or investor due diligence are delayed.

medium

Contingent consideration from asset sales may be lower

The ₹700 crore contingent consideration from BOT asset sales could be reduced to ~₹500 crore due to NHI claim uncertainties.

medium

Revenue concentration risk from project cancellations

One MSRDC project (₹279 crore) was cancelled due to scope changes; similar issues could affect other packages.

medium