Questions audited

12

Answered directly

79%

Numeric claims

3

Consistency

contradicted

Question ledger

What was answered, and how?

Viper Zukshi · JP Morgan

direct

Status of equipment procurement for new energy cell line.

the equipment has been ordered. Uh the bigger challenge that we've been facing is uh not so much that we don't have access to equipment but we have a little bit of limitations in terms of getting the engineers from China to come and help to actually commission the equipment.

Viper Zukshi · JP Morgan

partial

Progress on Gotion partnership and next steps.

the sharing of technology, licensing technology is something that's been largely uh you know discouraged by the Chinese government. This is hitting all players and their technical tryups pretty equally at the moment.

Viper Zukshi · JP Morgan

direct

Expected margins for the 5 GWh ESS plant once stabilized.

The operating margins should be around uh let's say 6 to 7% to start with. uh but we feel uh as opportunity progresses... there is an upside possible on these margins

Ragunan NL · Noama Research

direct

Growth rates for two-wheeler OEM, UPS, telecom, four-wheeler export in Q4 and FY27 outlook.

both the OEMs both in the four-wheeler as two-wheeler have grown more than 30% during the current quarter. Uh and uh after market was growing somewhere around 5 to 6% during the current quarter... Telecom obviously there is a degrowth

Ragunan NL · Noama Research

partial

Raw material cost mix, under-recovery, and expected price hikes.

about 70% of material between lead and alloys... plastics account for almost 10% of our raw material cost... at least another 2 to 3% kind of a price increase is something that we should look for

Ragunan NL · Noama Research

direct

Benefit from capital recycling in the quarter and future expectations.

Last quarter we have seen about 0.5% benefit coming from the recycling plant... there is a 5% accretion because of uh uh the recycling operation. We hope that will sustain in the coming quarters.

Ganesh · Unifi Capital

partial

Incremental buyer for scaling from 2 to 16 GWh and binding offtake.

We do build in a little bit of safeguards something more akin to kind of a take or pay kind of agreement... when we're building the 5 G ESS plant any up to that uh capacity whatever we're making in ESS cell we are the end user

Ganesh · Unifi Capital

partial

Cell cost per kWh vs imported cells and expected ROC on capex.

we're not going to be cost competitive with uh a product that's imported from China... China plus $15 to $20 is the minimum... if we can achieve a scale of about 8 to 10 gawatt hour work uh we see that there is a possibility of an IITA margin in the range of 10 to 11%.

Kapil Singh · Namura

partial

Medium-term margin outlook and risk of lead acid underutilization due to EV penetration.

we are still hopeful to reach a 13 to 14% kind of an AITA margin even at a two lakh kind of a lead day... we don't foresee an immediate problem with respect to our tubular batteries

Kapil Singh · Namura

direct

Core competence and key success factors in the BESS business.

a single 5 megatt hour container is almost a quarter million dollar of equipment... Amaraja is in a position to do a lot more localization domestic value addition... with policies coming in to mandate more domestic value addition I think a group like Amaraja is definitely in a better position

Janesh Gandhi · Oakland Capital

direct

Approvals for Gotion tie-up and timeline for LFP plant.

the deal earlier announced with goan is simply a corporate to corporate tie up. We've never sought any government approval... probably 2028 ending 2028.

Ganesh · Unifi Capital

direct

Localization expectations for BESS vs EVs and impact of customers making own cells.

we do expect that and we've already seen that battery packs are incurring a higher duty... by and large most of the OEMs that we're in touch with don't have plans to localize cells so they're in talks with players like us