Material risks this quarter

Lead price inflation and pricing action uncertainty

Lead prices have risen ~₹20,000/tonne; management has not yet taken pricing action, which could pressure margins if prices persist.

medium

Higher warranty provisions may persist for 2-3 quarters

Warranty provisions increased due to higher actual replacements; management expects elevated provisions for at least the next couple of quarters.

medium

EPR provision may not be fully reversible

A one-time ₹35 crore EPR provision was taken; if scrap collection does not improve, additional costs may arise, though monthly impact is expected to be <₹1 crore.

low

Chinese equipment export restrictions could delay cell plant

China's restrictions on equipment for lithium-ion cell manufacturing may cause minor delays, though management is exploring alternatives.