Delayed L1 conversions in Maharashtra
Four L1 projects in Maharashtra (total ~₹7,700 crore) face uncertainty due to land acquisition issues; management is engaging with the government but outcome is unclear.
Afcons Infrastructure · Material risks, their source context, and severity in the latest available quarter.
ConCallIQ research layer
Use the controls below to narrow the view, then follow the evidence into the next layer of context.
Risk intelligence
Four L1 projects in Maharashtra (total ~₹7,700 crore) face uncertainty due to land acquisition issues; management is engaging with the government but outcome is unclear.
₹450 crore receivables and ₹600-650 crore unexecuted work stalled due to client payment delays; work has been stopped and demobilized.
Second consignment of TBMs for high-speed rail project is stuck at port for two months; delay could push execution start to Q1 FY27.
Net debt rose to ₹2,714 crore due to delayed certifications and payment stretch; interest-bearing advances doubled to 40% of total advances.