AFCONS / Q2-FY26 / risks

Keep the risk register visible.

Afcons Infrastructure · Material risks, their source context, and severity in the latest available quarter.

Research layer active

ConCallIQ research layer

Signal, with the source still visible.

Use the controls below to narrow the view, then follow the evidence into the next layer of context.

WatchQ2-FY26 · 2025-10-30Back to quarter ↗

Risk intelligence

Material risks this quarter

Delayed L1 conversions in Maharashtra

Four L1 projects in Maharashtra (total ~₹7,700 crore) face uncertainty due to land acquisition issues; management is engaging with the government but outcome is unclear.

high

Jal Jeevan Mission payment stuck

₹450 crore receivables and ₹600-650 crore unexecuted work stalled due to client payment delays; work has been stopped and demobilized.

high

TBM consignment delay from China

Second consignment of TBMs for high-speed rail project is stuck at port for two months; delay could push execution start to Q1 FY27.

medium

Working capital and debt increase

Net debt rose to ₹2,714 crore due to delayed certifications and payment stretch; interest-bearing advances doubled to 40% of total advances.

medium